107/2012 The Cabinet noted the result of the first round of revenue monitoring for 2012/2013 and instructed Directors to come forward with further proposals for management action to reduce the potential deficit. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council. Where a budget overspend is forecast, Cabinet supported by the corporate management team must identify measures to remove any excess expenditure.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report details the revenue budget forecasts as at the end of Quarter 1 (April to June 2012) and highlights the major financial risks remaining in respect of the 2012/2013 General Fund revenue budget.
1. Budget and Policy Framework
1.1It is the responsibility of Cabinet to ensure that income and expenditure remains within the budget approved by Council.
1.2The Cabinet is asked to accept this report as urgent to enable Cabinet to receive and consider the latest performance monitoring information at the earliest opportunity.
Background
2.1At its meeting on 23 February 2012, the Council set a General Fund net budget requirement of £180.998 million for 2012/2013, whilst Council Tax continues to be frozen at 2010/2011 levels, on the back of a further ‘freeze grant’ offered by Central Government.
2.2This is the first quarterly report, summarising reports that have previously been submitted to directorate management teams, based on returns from individual budget managers. In preparing their returns budget managers have been asked to take account of last years outturn, actual income and expenditure for the year to date and, most importantly, their knowledge of commitments and service requirements anticipated for the remainder of the financial year. 2.3. Table 1 below contains a summary of the Council’s forecast position, with further detail, at divisional level and before management action, included at Appendix 1.
2.4The individual amounts shown against services differ from the totals agreed by the Council at budget setting in February. There are three main reasons for this. The first is a change in the level of DSG arising from the January pupil count albeit this is a nil effect being net against the DSG funded services in the table. The second is the move of Housing Services from Business Support (BSD) to Regeneration, Community and Culture (RCC). The third and most complex relates to the various changes arising from a combination of responsibility transfers and allocation of savings from the ‘Better for Less’ project (BfL). All of these changes are set out in Appendix 6 but it should be noted that there remains a sum still to be identified for ‘Better for Less’ savings within the BSD total.
3. Summary Revenue Budget Position 2012/2013
3.1It can be seen from Table 1 that, after management action, the outturn forecast for 2012/2013 currently stands at just under a £1 million overspend which is a much better position than at this time last year when the equivalent forecast was for a £4.0 million overspend.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.