Resolved
The committee noted the forecast outturn position fro 2012/2013 and any proposed management action to reduce the potential deficit.
Business Support Overview and Scrutiny Committee noted this item on Thursday 6 December 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
The committee noted the forecast outturn position fro 2012/2013 and any proposed management action to reduce the potential deficit.
This report details the revenue budget forecasts as at the end of Quarter 2 (April to September 2012) and highlights the major financial risks remaining in respect of the 2012/2013 General Fund revenue budget
1. Budget and Policy Framework
1.1It is the responsibility of Cabinet to ensure that income and expenditure remains within the budget approved by Council.
2.1Cabinet Members, in considering this report on 30 October, were requested to note the forecast position from the second quarter’s revenue monitoring for 2012/2013 and any proposed management action.
2.2At its meeting on 23 February 2012, the Council set a General Fund net budget requirement of £180.998 million for 2012/2013, whilst Council Tax continues to be frozen at 2010/2011 levels, on the back of a further ‘freeze grant’ offered by Central Government.
2.3This is the second quarterly report, summarising reports that have previously been submitted to directorate management teams, based on returns from individual budget managers. In preparing their returns budget managers have been asked to take account of last years outturn, actual income and expenditure for the year to date and, most importantly, their knowledge of commitments and service requirements anticipated for the remainder of the financial year. 2.4. Table 1 below contains a summary of the Council’s forecast position, with further detail, at divisional level and before management action, included at Appendix 1.
3. Summary Revenue Budget Position 2012/2013
3.1It can be seen from Table 1 that the outturn forecast for 2012/2013 currently stands at a £961,000 overspend, an improvement of £5,000 on the previous quarter although there are no proposals for further management action.
Table 1: Quarter 2 Summary Budget Forecast Proposed Q2 Q1 Directorate 2012/2013 variance action variance variance £000s £000s £000s £000s £000s Children and Adult Services: - DSG funded services 127,347 0 0 0 0 - General fund services 124,856 726 0 726 329 Regeneration, 57,385 500 0 500 745 Community and Culture Business Support 8,898 365 0 365 252 Public Health 283 (1) 0 (1) (5) Interest & Financing 15,442 (550) 0 (550) (276) Levies 974 (79) 0 (79) (79) Dedicated Schools (128,693) 0 0 0 0 Grant Council Tax Freeze (2,477) 0 0 0 0 Grant Specific Grants (23,017) 0 0 0 0
Budget Requirement 180,998 961 0 961 966
Council Tax (99,080)
Formula Grant (80,743)
Use of Reserves (1,175) 4. Children and Adult Services
4.1The directorate is currently forecasting a £726,000 overspend, the principal reasons for which are: £1,085,000 pressure in Children’s Care, driven by an increase in the number of looked after children having to be placed through expensive independent fostering agencies, as in-house capacity has been exhausted; A significant underspend against the budget for school early retirements and redundancies (£329,000). This is due to the local authority having fewer schools following academy conversions and the change in policy to make schools responsible for costs arising from their own restructuring proposals
4.2Demographic pressures within disability services have been offset by the availability of additional Primary Care Trust (PCT) income to fund expenditure on enablement, including homecare and adaptations.
4.3The directorate management team had previously proposed a number of measures to manage cost pressures within the Children’s Care division, but owing to insufficient senior management capacity due to absences, implementation of this action has been delayed and it has been deemed imprudent to provide an estimate of the financial impact at this stage.
5. Regeneration, Community and Culture
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revenue budget monitoring 2012/2013: quarter 2Report | 104 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.