Gateway 3 Contact Award: Wainscott Primary School: New Buildings for Expansion to Two Forms of Entry

Approved Executive 1 paper

Cabinet approved this item on Tuesday 18 December 2012. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

230/2012 The Cabinet approved the Final Business Case for the expansion of Wainscott Primary School to 2 forms of entry . 231/2012 The Cabinet agreed the award of the contract to construct new buildings for Wainscott Primary School to BAM Construction Limited using the EFA Design & Build Lump Sum Contract for use with the EFA Contractor Framework and to delegate authority to the Director of Children and Adult Services, in consultation with the Portfolio Holder for Children’s Services and the Assistant Director of Legal & Corporate Services to finalise the contract.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report presents the Final Business Case for the expansion of the buildings at Wainscott Primary School to accommodate 2 forms of entry following consideration at Procurement Board, along with the associated contract documents, and asks for Cabinet approval to finalise the formal contract with BAM Construction Limited, within the funding available and identified in the body of this report.

1. Budget and Policy Framework 1.1 The Wainscott Primary School final business case presents the proposals for the new building at the existing school site to allow for expansion to 2 forms of entry, as planned in the Capital Programme and following approval by Cabinet of the outline business case and Gateway 1 on 7 August 2012 (decision 111/2012) 1.2 The new buildings will be funded by the Department for Education Basic Need Grant, developer contributions from the Liberty Park development and capital receipts from the sale of education land. 1.3 The final business case is a key stage in the procurement process and is presented with the various contractual documents that support the financial close for the Wainscott Primary School expansion to 2FE. 1.4 Procurement Board has recommended that this report is presented to Cabinet for approval of financial close on the new building project for Wainscott Primary School and the award of the contract to BAM Construction Limited, through use of the Future Schools Agreement approved by Cabinet in February 2011 (decision 37/2011). 2. RELATED DECISIONS 2.1 Wainscott Primary School has been identified for expansion to accommodate increasing pupil numbers arising from the Liberty Park development as well as the movement of families into the Medway area. Following the Cabinet decision on 1 November 2011, (decision number 143/2011), a public consultation commenced in January 2012 on the proposals to make prescribed alterations to Wainscott Primary School to:

expand the lower age limits and size of buildings; increase the number of pupils from 1FE to 1.5FE.

The outcome of the consultation and any subsequent prescribed alterations to the school was presented to Cabinet on 17 April 2012 and it was agreed to undertake the statutory consultation (decision no. 66/2012). Following the statutory consultation, there were no objections to the proposals and the determination was completed under delegated powers of the Director of Children & Adults Services, in consultation with the Portfolio Holder for Childrens Services on 23 July 2012. The purpose of the associated building project is to provide accommodation to enable up to an additional 2FE to be accommodated at Wainscott Primary School. Current analysis of pupil need in Wainscott shows there will be a need to accommodate an additional 0.5FE at Wainscott Primary School for September 2013, with a further requirement to accommodate a further 0.5FE extra pupils in September 2014.

2.2On 15 February 2011, Cabinet approved the list of schools on the Future Schools Agreement (decision 37/2011) including Wainscott Primary School. This decision gives the Council the option to issue a notice to BAM Construction Limited, the Framework Contractor, to provide a proposal for the expansion of Wainscott Primary School in accordance with the brief. Following consultation with the Council’s procurement team and external legal advisors, this is the route that will give best value for money and the most expedient programme. Further details on the procurement options and the advice received are outlined below in section 6.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contact Award: Wainscott Primary School: New Buildings for Expansion to Two Forms of EntryReport 61 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
RC
Councillor Rodney Chambers, OBE (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
DB
Councillor David Brake (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
ND
Neil DaviesOfficer, in attendance
MH
Mick HaywardOfficer, in attendance

All 17 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Contact Award: Wainscott Primary School: New Buildings for Expansion to Two Forms of EntryThis decision
  2. Gateway 3 Contract Award - Family Time (Contact Service) for Children in Care and Their FamiliesAgreed
  3. Gateway 1 Procurement Commencement - Family Time (Contact Service) for Children in Care and FamiliesApproved
  4. Gateway Three Contact Award - Procurement and Maintenance of Bus Passenger SheltersApproved

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies