AUDIT COMMITTEE 25 SEPTEMBER 2013 INTERNAL AUDIT WORK PROGRAMME Report from: Internal Audit
Author: Alison Russell, Audit Services Manager
Summary To advise Members of progress in delivering the approved 2012/13 and 2013/14 work programme, and probity and follow up work undertaken since the last Audit Committee Meeting.
1. Budget and Policy Framework 1.1 It is within the remit of the Audit Committee to take decisions regarding accounts and audit issues.
2. Background – 2013/14 Programme
2.1Members approved the internal audit 2013/14 work programme on 21 March 2013 for year ending 31 March 2014. The programme is derived using a risk based approach to ensure that the assurance provided by Internal Audit through this work is of added value to the council.
2.2Audit work on the key financial systems, and the specific reviews of corporate governance and risk management, are considered key activities and are given priority when resources are allocated. The aim is that all of the key assurance audits will be completed prior to the approval of the annual governance statement.
2.3Progress to date on the 2013/14 plan is set out at Annex A. Progress on follow-ups is recorded in Annex C, and progress on the probity reviews is recorded in Annex D.
2.4The Audit Programme is reviewed in year to reflect any changes of priority in year. Any proposed changes are presented to the Audit Committee for approval. 3. Progress on prior year audit plans
3.1Outstanding audits from prior year audit plans are reported in Annex B.
4. Risk Management, Financial and Legal implications
4.1There are no risk management, financial or legal implications arising directly from this report.
5. Recommendations 5.1 Members are asked to note the progress in completing the 2012/13 and 2013/14 audit programmes.
Lead officer contact Name Alison Russell Job Title Audit Services Manager Telephone: 01634 332355 Email: [email protected]
Background papers Internal Audit Work Programme 2012/13, 29 March 2012 Internal Audit Work Programme 2013/14, 21 March 2013 ANNEX A
Audit Plan 2013/14
Authority Wide
Regeneration Children and
and Culture Community
Business Support Activity
Health Adults Key Financial Systems Council Tax Q4 Local Business Rates (1) DR (Review of introduction) Local Business Rates (2) Q4 Housing Benefit Q4 Housing Rents Q4 Other Financial Systems Procurement Q3 Social Care Payments Q3 Q3 Payroll F PCIS Compliance Q3 Local Income Management Q4 Q4 Visitor Information Centre AC 07/13 The Villager (minibus hire) AC 09/13 Trading Standards AC 09/13 Duke of Edinburgh Awards AC 09/13 Handitills F F Lifeline F Upnor Castle DR School Financial Management Q4 Q4 Risk Assessed Audits (CHECK) Local Welfare Provision P Better for Less Q3 Health Commissioning Q3 Foster Care (DBS and DP) F Capital Projects Q3 Innovation Centre Medway AC09/13 Grant Payments Q2 Rural Liaison Grant AC 09/13 Adaptations F Success F Data Quality P Audit Plan 2013/14
Authority Wide
Regeneration Children and
and Culture Community
Business Support Activity
Health Adults Asset Management - F Divestments DBS – central processes F NORSE P Governance Audits Risk Management Q4 Corporate Governance Q4 National Fraud Initiative AC 09/13
Annex B
Internal Audit Programme 2012/13 Regeneration Children and
and Culture Community
Business Authority
Support Activity Health Adults Wide
Procurement (Category F Management approach) Partnerships P Maintenance Contracts F Carbon Reduction AC 09/13
KEY AC = month & year reported to Audit Committee DR = draft report issued F = fieldwork in progress P = audit in planning stage Bold = audits are reported to this Audit Committee Annex C
Follow Ups Undertaken Follow Ups Undertaken 2013/14 Date to Audit Committee Debtors Income AC 09/13
Follow Ups Pending Follow Up Status Schools Local Bank Accounts Full follow up not due IWorld System - Access Controls Full follow up not due Waste Management Contract Full follow up not due HR Data Security In progress
Annex D
Probity Reviews 2013/14 Review Status
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Work ProgrammeReport | 30 KB | DownloadRead as text |
Follow Audit Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Internal Audit Strategy 2025-28 Progress UpdateThe Committee noted the progress during 2025-26 against the Internal Audit Strategy 2025-28. | Noted | Open |
| 30 Jul 2026 | National Fraud Initiative Exercise - Annual UpdateThe Committee noted the report. | Noted | Open |
| 30 Jul 2026 | Audit Committee - Review of Terms of ReferenceThe Committee approved the suggested changes to Terms of Reference and provide a recommendation to Full Council for a... | Approved | Open |
| 30 Jul 2026 | Exclusion of the press and publicThe Committee agreed not to exclude the press and public and defer the item to the following meeting. | Agreed | Open |
| 19 Mar 2026 | Internal Audit Update 1 December 2025 to 28 February 2026The Committee noted the outputs and performance against the Internal Audit Plans for Medway for the period 1 December... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.