The Audit Committee noted (a) that an update report on progress of the work programme would be provided to the Audit Committee in January 2015; (b) the progress on the 2014/15 audit programme, and the outcome of Internal Audit’s work.
Audit Committee noted this item on Thursday 25 September 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
The Audit Committee noted (a) that an update report on progress of the work programme would be provided to the Audit Committee in January 2015; (b) the progress on the 2014/15 audit programme, and the outcome of Internal Audit’s work.
2.1Annual audit programmes, approved by the Audit Committee each March, are derived using a risk based approach to ensure that the assurance provided by Internal Audit through this work is of added value to the council.
2.2Annual audit programmes include audits of key financial systems and annual governance reviews, which are considered key activities and are given priority when resources are allocated.
2.3Members approved the internal audit 2014/15 work programme on 20 March 2014 for year ending 31 March 2015. Progress to date on the 2014/15 plan is set out at Annex A. This progress document includes any outstanding audit reports relating to the 2013/14 work programme.
2.4The Audit Programme is reviewed in year to reflect any changes of priority since the plan was approved. Any proposed changes are presented to the Audit Committee for approval.
2.5This report also contains the outputs from each audit completed since the last update to the Committee. These are set out in Annex B. Each audit and follow up provides assurance over the appropriateness and effectiveness of the control arrangements in place. Controls are assessed in terms of whether they mitigate the identified risks, and maximise the likelihood of achieving stated objectives. Each output has been shared and agreed with management. A list of grant and payment by results certification is also included in this annex.
2.6The definitions of the recommendation and audit opinion options, as endorsed by Audit Committee in July 2013, are shown at Annex C.
2.7An overall audit opinion is provided for each full audit. Audit opinions are not provided in the outputs of individual probity and site reviews, but these outputs form the basis of full audit reports which will contain an opinion on the council-wide procedures in place.
2.8All audit recommendations are shared with management and agreed actions recorded, along with the implementation date and the officer responsible. The agreed management action plan relating to significant or material recommendations is incorporated in the issued final audit report, and summarised for Audit Committee.
2.9Internal Audit obtains confirmation of progress on recommendations made, usually within six months. Where the overall audit opinion is that the control arrangements “need strengthening” or are “weak” a follow up is undertaken of the revised arrangements. The original audit opinion is reviewed in light of these findings, and the outputs of these follow ups are presented to Audit Committee.
2.10The audit programme includes audits of key financial systems and governance reviews, which are considered key activities and are given priority when resources are allocated.
Internal Audit Resources
2.11The internal audit team is presently running with only two of the four auditor posts filled. There is one vacancy as a result of a resignation with effect from September 2014 and the other post is unfilled as a result of a secondment arrangement which is likely to become a permanent transfer. A recruitment exercise is currently underway to fill the substantive vacancy and a secondment from finance has been agreed to back-fill the other post until March 2015, but with agreement to recruit on a permanent basis should the vacancy become substantive. Confirmation of any proposed amendment to the audit plan needed as a result of these staffing issues will be presented to the Audit Committee in January 2015 for consideration and approval.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit ProgrammeReport | 72 KB | DownloadRead as text |
Follow Audit Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Internal Audit Strategy 2025-28 Progress UpdateThe Committee noted the progress during 2025-26 against the Internal Audit Strategy 2025-28. | Noted | Open |
| 30 Jul 2026 | National Fraud Initiative Exercise - Annual UpdateThe Committee noted the report. | Noted | Open |
| 30 Jul 2026 | Audit Committee - Review of Terms of ReferenceThe Committee approved the suggested changes to Terms of Reference and provide a recommendation to Full Council for a... | Approved | Open |
| 30 Jul 2026 | Exclusion of the press and publicThe Committee agreed not to exclude the press and public and defer the item to the following meeting. | Agreed | Open |
| 19 Mar 2026 | Internal Audit Update 1 December 2025 to 28 February 2026The Committee noted the outputs and performance against the Internal Audit Plans for Medway for the period 1 December... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.