Approved, subject to the completion of Section 106 Agreement and conditions 1-16, as set out in the Committee report and with two additional conditions: 17. Prior to the bringing into use of the development hereby approved, a litter mitigation strategy to address the issue of litter from the drive through restaurant in the surrounding area, shall be submitted to and approved in writing by the Local Planning Authority. The approved strategy shall be implemented upon commencement of operation and shall thereafter be maintained unless amendments are agreed in writing with the Local Planning Authority. Reason: To address issues of litter from the drive through restaurant in the local area in the interests of amenity. 18. Prior to the bringing into use of the development hereby approved, a traffic management strategy, to address potential issues regarding vehicle conflict between delivery lorries to Tesco and customers of the drive through restaurant and to avoid queues back onto the public highway or HGV parking on the public highway, shall be submitted to and approved in writing by the Local Planning Authority. The approved strategy shall be implemented and thereafter maintained unless amendments are otherwise agreed in writing with the Local Planning Authority. Reason: In the interests of highway safety and the free flow of traffic.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Location: Land Adjacent To Tesco's, Courteney Road, Rainham, Gillingham
Proposal: Construction of two-storey restaurant with associated drive-thru, car parking, landscaping and associated works; installation of 2no customer order display units with associated canopies and gateway height restrictor.
Applicant: McDonalds Restaurant Ltd
Agent: [name removed], Planware Ltd, The Granary First Floor, 37 Walnut Tree Lane, Sudbury, Suffolk CO10 1BD
Recommendation of Officers to the Planning Committee, to be considered and determined by the Planning Committee at a meeting to be held on 29 June 2016.
Recommendation - Approval subject to:
A The applicant entering into an agreement under Section 106 of the Town and Country Planning Act to secure a contribution of £1,000 towards initiatives to combat obesity; and
B. And the following conditions:-
1 The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To comply with Section 91 of the Town and Country Planning Act 1990 (as amended).
2 The development hereby permitted shall be carried out in accordance with the following approved plans:
Drawing numbers 6926-PL-005B and 6926-PL-006B and drawings showing COD canopy, fencing details, patio fencing elevation & Euroline Furniture details received on 2 February 2016; drawings and details electricity kiosk 1 and 2 received on 15 February 2016; drawing number 6926-PL-002E received on 16 February 2016; and 6926-PL-004E received on 17 February 2016; and drawing numbers D143155/2 and MK MCD GT 01 A received on 25 February 2016. Reason: For the avoidance of doubt and in the interests of proper planning.
3 Unless otherwise agreed by the Local Planning Authority, development other than that required to be carried out as part of an approved scheme of remediation must not commence until conditions 4 to 7 have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified in writing by the Local Planning Authority until condition 7 has been complied with in relation to that contamination.
Reason: Required before commencement of development to avoid any irreversible detrimental impact on human health and/or water courses as a result of the potential mobilising of contamination and in accordance with Policy BNE23 of the Medway Local Plan 2003.
4 A desk top study, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, including risks to groundwater, whether or not it originates on the site. The scheme shall be submitted to and approved in writing by the Local Planning Authority prior to commencement of the development. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report shall be submitted to and approved by the Local Planning Authority prior to the commencement of development. The report of the findings must include:
(i) a survey of the extent, scale and nature of contamination;
(ii) an assessment of the potential risks to:
human health Property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes. adjoining land, groundwaters and surface waters, ecological systems, archaeological sites and ancient monuments;
(iii) an appraisal of remedial options, and proposal of the preferred option(s).
This must be conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11'.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.