The Cabinet noted the comments of the Regeneration, Culture and Environment Overview and Scrutiny Committee as set out in paragraph 7 of the report. 98/2017 The Cabinet approved the declaration of the new Air Quality Management Area (AQMA) at Four Elms Hill to ensure Medway’s statutory duty, under the requirements of the Environment Act 1995, are met and instructed officers to: · undertake the necessary work to formally declare the area as an AQMA; · develop and consult on an Action Plan for the area; and · report back to Cabinet to gain approval of the new Action Plan. Reasons: Medway has a statutory duty under the Environment Act 1995 to declare an AQMA where the air quality objectives are not being met. By Cabinet approving the declaration of the new AQMA at Four Elms Hill this will also provide Medway with some protection against potential infraction fines being passed down to the local authority by Central Government.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
The purpose of the report is to inform Cabinet of the findings of the consultation which has been undertaken to inform statutory consultees and members of the public of the need to declare a new Air Quality Management Area (AQMA) at Four Elms Hill prior to the formal declaration of the AQMA. The area needs to be declared to satisfy the requirements of the Environment Act 1995 and the declaration will be a publicly available document.
1. Budget and Policy Framework
1.1Local authorities have a duty under the Environmental Act 1995 to declare an AQMA where the air quality objectives are not being met. The decision to declare the area as an AQMA is one which needs to be made by Cabinet.
1.2Once an AQMA has been designated local authorities are required to develop an Action Plan, detailing the measures it will implement to tackle the problem. Development of the plan should take no longer than 12 months from the time of declaration. It is envisaged that the measures within the current Medway Air Quality Action Plan (AQAP) (approved by Cabinet on 15 December 2015) will also have a positive impact on the new AQMA. The AQAP will need to be amended to accommodate the new AQMA and any new corresponding measures, as appropriate. The impact that the Council can have on air quality is limited by the feasibility and practicalities of the measures which can be implemented.
1.3Air quality is referenced within the Local Transport Plan under Priority 2 – To support a healthier natural environment by contributing to tacking climate change and improving air quality, and Transport Objective 4 – Encouraging active travel and improving health. This objective links to air quality legislation. Air quality in general terms features in the Local Plan 2003 and Policy BNE24 deals with air quality. If approval is obtained from Cabinet, the formal declaration of the new AQMA will be submitted to Defra.
Background
2.1Local authorities have a duty under the Environmental Act 1995 to declare an AQMA where the air quality objectives are not being met. It is important that a local authority is confident it has identified an exceedance of the objectives; usually through a combination of monitoring and modelling data.
2.2Monitoring has been undertaken in the area and the monitoring data for 2015 shows that annual average levels of nitrogen dioxide have exceeded the Government’s limits at Four Elms Hill, Chattenden. This area is currently outside of any of the declared Medway AQMAs.
2.3Medway’s Annual Status Report for 2016, which was submitted to Defra on 12 August 2016, recommended that a Detailed Assessment was undertaken to:
Confirm the need to declare an AQMA at Four Elms Hill Determine the spatial extent of the AQMA Provide relevant information for the development of action plan measures.
2.4The Detailed Assessment (Appendix 1) was completed in November 2016 and confirmed the need to declare a new AQMA at Four Elms Hill, and identified that 24 residential properties are likely to lie within the exceedance area.
2.5The council is required to undertake a statutory consultation on the AQMA declaration prior to the formal declaration of the AQMA by legal order. The consultation was undertaken between 23 May and 28 June 2017 and engaged with statutory consultees, members of the public and other interested parties.
Options
3.1The options given below relate to the next steps available to the council now that the statutory consultation has been completed.
Option 1: Formal Declaration of AQMA and Development of an Action Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.