111/2017 The Cabinet approved option 1, the expansion of the partnership, through the inclusion of Canterbury City Council’s building control service. Reasons: The expansion of the partnership will build in further resilience and provide opportunities for a wider market and broader customer base as well as providing reductions in contributions for the existing three partners.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks approval from Cabinet to extend the South Thames Gateway Building Control Partnership by the inclusion of Canterbury City Council’s building control service.
1. Budget and Policy Framework
1.1The approval of the South Thames Gateway Building Control Partnership expansion is a matter for Cabinet, however, specific parts of the business case may need to be progressed in accordance with the Council’s relevant policies and procedures.
1.2Following a requirement of The Memorandum of Agreement which underpins the Partnership, each of the existing partnership councils shall first agree to the additional authority joining. Before the authority joins a due diligence investigation and evaluation of benefits shall be carried out and presented to Joint Committee.
Background
2.1Following an approach by Canterbury City Council the partnership engaged in a project to examine the viability of them joining as a fourth partner.
2.2Members of Joint Committee instructed that any expansion could only be considered at nil detriment to the existing arrangements. Not only would that mean no increase to their forecasted contributions but also equally important was to ensure the excellent reputation of the partnership and the high quality service to customers would be maintained. 2.3 An Outline Business Case was taken to Joint Committee in June 2017 and following their consideration and recommendations the attached business case (exempt appendix) has been developed through negotiation and discussion between the partnership and Canterbury City Council. The Joint Committee is considering a further report on the expansion proposals on 21 September 2017 and its comments will be reported to Cabinet.
2.4Through the development of the partnerships digitalisation programme and the creation of a business model using agile and mobile working the partnership has been able to demonstrate how improvements to customer service and service delivery can be achieved. Through the effective use of borderless office principles the model can be incorporated in this and future partnership expansion plans.
2.5A financial forecast within the business case demonstrates further reductions in contributions by the existing three partners to 2021 should this proposal be taken forward. There are also details of the operational plan and revised staffing structure to verify the viability of the project.
Options
3.1The partnership has been operated successfully over the last 10 years and Members of Joint Committee have expressed a view to share some of the benefits from the operation with the adjoining authorities and to also enhance the resilience and opportunities through a wider market that expansion would bring.
3.2Option 1 is to approve expansion of the partnership to include Canterbury City Council building control service, thus increasing the potential market for services and building in resilience to the service through the inclusion of additional staff who are not constrained by existing boundary arrangements. The financial plan included in the business case demonstrates the potential for increased income generation and a reduction in the contributions that the three existing partners pay for public protection services.
3.3Option 2 is to remain as we are further examining the potential for improved services using technology.
4. Advice and analysis
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.