The Committee: a) noted the report and thanked the Head of Planning and his staff for the performance of the planning function over the past 6 months and requested that the Head of Planning pass on the Committee’s appreciation to staff; b) requested that the Head of Planning arrange briefings for Members of the Committee on the proposals within the budget aimed at preventing developers from delaying the development of land and the provision of infrastructure; and c) requested that the Head of Planning provide the Chairman and the Ward Councillors for Rainham North with the current costs from consultants associated with a particular enforcement case.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report is presented quarterly to committee informing Members on current Planning performance and the Local Plan.
1. Budget and Policy Framework
1.1There are no budget and policy framework decisions arising directly from this report. This is an information item for the Planning Committee.
Background
2.1Performance relating to the processing of planning applications is collected as National Indicator 157. The NI157 targets are:
Major developments: to determine 60% of applications within 13 weeks.
Minor Developments: to determine 70% of applications within 8 weeks.
Other Developments: to determine 70% of applications within 8 weeks.
3. Performance
3.1See attached charts in Appendices A to G for performance concerning the processing of planning applications, benchmarking, appeals, enforcement activity, Tree Preservation applications and a breakdown of complaints received. 3.2 During the period 1 April 2017 to 30 September 2017 the authority received 801 planning applications; this is compared to 778 for the same period in 2016. For the year 2016/17 the authority received 1543 applications, this compares to 1421 in 2015/16.
Performance for applications is split between those subject to an extension of time and those not. An extension of time can be in the form of a Planning Performance Agreement (PPA) or a Planning Extension Agreement (PEA).
Performance for major applications not subject to an extension of time during the six month period is 83.33%. Applications subject to an extension of time is 94.12%. This is against a target of 60%.
Performance for minor applications not subject to an extension of time during the six month period is 95.37%. Applications subject to an extension of time is 85.29%. This is against a target of 70%.
Performance for other applications not subject to an extension of time during the six month is 97.07%. Applications subject to an extension of time is 85.45%. This is against a target of 70%.
Appendix A, figures 2, 3 and 4 show performance against target (including those not subject and those subject to an extension of time) for majors, minor and other applications for the year.
Comparing performance against the latest data available nationally (April to June 2017), Medway performed significantly above the national average for minor and other applications but slightly below the national average for major applications (see Appendix B).
Pressure on officer resources has been carefully managed in order to meet national performance targets. This pressure continues and with the added pressure of annual leave, maternity leave and vacancies, the workload will need to be carefully managed if performance is to continue to be maintained. Two additional Planners and one additional Senior Planner have been appointed, initially paid from PPA payments, to assist in dealing with workload pressures.
3.3During the six month period, 140 applications with Planning Extension Agreements were decided; this compares to 155 in the previous six months (see Appendix C). Comparing performance against national data for the period April to June 2017, 88% of applications were determined within the agreed extended timeframe nationally compared to 86% by Medway.
3.4Five Planning Performance Agreements (PPA’s) were entered into during the six month period. These related to:
Chatham Quayside (Formerly Colonial House) Bakersfield Land south of Ratcliffe Highway 25 Corporation Street, Rochester - 140 bed hotel development Chattenden Lane, Chattenden – Up to 530 dwellings
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.