Resolved
The Committee agreed to approve the Audit and Counter Fraud Quality Assurance and Improvement Programme, subject to the wording of Indicator PM24 being revised.
Audit Committee agreed this item on Tuesday 9 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to approve the Audit and Counter Fraud Quality Assurance and Improvement Programme, subject to the wording of Indicator PM24 being revised.
2.1The Public Sector Internal Audit Standards (Standards) require that: The chief audit executive must develop and maintain a quality assurance and improvement programme that covers all aspects of the internal audit activity. On 10 January 2017, the Audit Committee approved the Quality Assurance & Improvement Programme (QAIP) prepared to meet this requirement.
3. Review of the QAIP
3.1The QAIP was prepared to reflect both the integration of counter fraud and the shared service with Gravesham Borough Council and was designed to meet the requirements of the Standards and CIPFA’s Local Government Application Note to the Public Sector Internal Audit Standards.
3.2The QAIP has been reviewed and is considered to continue to meet these requirements and will therefore continue to be in place for the coming financial year, however there are some proposed amendments to the performance measures and the table in which they are presented. The changes are detailed below and the revised QAIP is presented for Members approval at Appendix 1.
3.2.1. While all the performance measures are still based on the balanced scorecard approach, the table documenting the measures is now laid out to reflect information provided that relates to the Audit & Counter Fraud Shared Service as a whole and those that are specific to either Medway or Gravesham. 3.2.2. PM1 – Cost of the Audit & Counter Fraud Service compared to the 2015-16 baseline year budgets: This has been split into a) the total cost of the Audit & Counter Fraud Service and b) the split of those costs for Medway or Gravesham.
3.2.3. PM2 – Audit & Counter Fraud day: the target costs have been set at £400 based on an outturn of £376 in the year to date and to take into account any annual increases in staff costs for 2018-19.
3.2.4. PM3 - Proportion of staff with relevant professional qualification: the target has been increased to 75%. Previously this only took into account staff attaining a professional audit qualification. It now takes into account both audit and counter fraud qualifications.
3.2.5. PM10 - Proportion of productive time spent on a) assurance work b) consultancy work: The target has been increased from 55% to 65% to reflect the planned split of resources for audit and counter fraud work.
3.2.6. PM11 - Proportion of productive time spent on a) proactive counter fraud work b) reactive counter fraud work: The target has been reduced from 45% to 35% to reflect the planned split of resources for audit and counter fraud work.
3.2.7. PM12 – Proportion of agreed assurance assignments a) Delivered b) Underway: This was previously ‘Proportion of agreed plan delivered’ but has been amended to more accurately reflect the monitoring of assurance reviews by showing the proportion delivered and proportion also underway. This gives Members a much clearer picture of progress against the target.
3.2.8. PM17 - Proportion of recommended actions implemented by agreed date: The target for this performance measure has been removed as the Audit & Counter Fraud Service has no control over the outturns. Implementation of recommendations is the responsibility of the services to which the recommendations were made. The performance will continue to be reported to Members to ensure they are aware of any significant issues.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 280 KB | Download |
PDF |
Review of Audit and Counter Fraud Quality Assurance and Improvement ProgrammeReport | 130 KB | DownloadRead as text |
Follow Audit Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Internal Audit Strategy 2025-28 Progress UpdateThe Committee noted the progress during 2025-26 against the Internal Audit Strategy 2025-28. | Noted | Open |
| 30 Jul 2026 | National Fraud Initiative Exercise - Annual UpdateThe Committee noted the report. | Noted | Open |
| 30 Jul 2026 | Audit Committee - Review of Terms of ReferenceThe Committee approved the suggested changes to Terms of Reference and provide a recommendation to Full Council for a... | Approved | Open |
| 30 Jul 2026 | Exclusion of the press and publicThe Committee agreed not to exclude the press and public and defer the item to the following meeting. | Agreed | Open |
| 19 Mar 2026 | Internal Audit Update 1 December 2025 to 28 February 2026The Committee noted the outputs and performance against the Internal Audit Plans for Medway for the period 1 December... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.