9/2018 The Cabinet agreed to insert the words “and/or” in replacement of “/” in line 5 of Table 1 of paragraph 2.13 in the report. 10/2018 The Cabinet recommended to Full Council to add the supplementary project costs in respect of the Strood Flood Management Works scheme, as set out in section 2 of the report to the Capital Programme. Reasons: Additions to the Capital Programme are a matter for Full Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report provides details of the Strood Flood Management Works scheme which requires Full Council approval to be added to the Capital Programme.
The Cabinet is requested to recommend this addition to Full Council for final consideration and approval.
1. Budget and Policy Framework
1.1It is the responsibility of Cabinet to ensure that expenditure for each capital scheme remains within the budget approved by the Council but it remains the responsibility of Council to approve schemes for inclusion in the capital programme.
2. Strood Flood Management Works
2.1The Strood Waterfront site represents a significant brownfield redevelopment opportunity and has long been on the regeneration agenda for Medway Council. The site is owned by Medway Council.
2.2In 2008, planning permission was secured for the construction of a river wall around the site. Changing market conditions at the time that the planning permission was granted for the river wall resulted in the site not coming forward for development.
2.3Subsequent Environment Agency requirements for the river wall meant that costs would be in excess of the budget. Therefore a flood mitigation optioneering study was undertaken in August 2015, to determine the most appropriate and cost effective flood mitigation solution for Strood Riverside, taking into account the nature of the proposed development.
2.4Council approved the proposal to complete the flood defences for Strood in two phases, which would allow for the development and regeneration of Strood Waterfront to now include the former Civic Centre site.
2.5The works involve installation of a sheet pile wall around the perimeter of the site and then filling the ground by approximately two metres to protect the site from tidal flooding.
2.6The works will change the alignment of Canal Road to provide more developable land each side of the road and to allow for more residential units on the riverside; it is also proposed to move the station approach road slightly to provide a direct link and views from Strood Station down to the river and pier, giving passengers a sense of arrival and orientation.
2.7The proposed solution will allow for maximum use of waterfront land to deliver circa 1166 quality homes with stunning views across to Rochester Cathedral and Castle; 602 on Riverside and 564 on the Civic site. Delivering these housing units will help meet the council target of 29,500 new homes by 2035.
2.8As a result of the works and the subsequent development, approximately 2,500 jobs will be created.
2.9The flood mitigation works will enable a feasible, flood resilient, mixed use regeneration site, and remove the isolation of the surrounding developments. The proposed new developments will complement the nearby Innovation Studios Strood, as a satellite of the Innovation Centre Medway.
2.10Regeneration will thus provide employment land, targeted at SMEs, encouraging local cafes and restaurants, enabling job creation and innovation, as well as encouraging a vibrant environment where people will enjoy living and socialising and grow the local economy. In particular, it will enable the development of the former Civic Centre site as the most prestigious development site in Medway.
2.11The planning applications for the flood risk management works for both sites were submitted in May 2017 and approval was given at Planning Committee on 22 November 2017.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.