The Cabinet noted the comments of the Business Support Overview and Scrutiny Committee set out at section 6 of this report 78/2018 The Cabinet approved the amendments proposed to the Corporate Risk Register as detailed in Appendices A and B to the report. Reasons: The establishment of a corporate framework for risk management is recommended by CIPFA and SOLACE and will complement and support the work already being carried out within each directorate to manage risks.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
CABINET 8 MAY 2018 SIX MONTHLY REVIEW OF THE CORPORATE RISK REGISTER Portfolio Holder: Councillor Rupert Turpin, Business Management
Report from: Phil Watts, Chief Finance Officer / Chair of Strategic Risk Management Group
Author: Katey Arrowsmith, Head of Finance Strategy
Summary In accordance with paragraph 4.1 of the Council’s Risk Management Strategy, this report is to discuss the 6 monthly review of the Council’s Corporate Business Risk Register.
The Cabinet is invited to consider this report, including the comments of the Business Support Overview and Scrutiny Committee which considered the report on 12 April 2018.
1. Budget and Policy Framework 1.1 The Risk Management Strategy underpins all aspects of Council work and is fundamental to the Council Plan in terms of "giving value for money”. 2. Background 2.1 Risk management is an integral part of good governance. The Council recognises that it has a responsibility to identify and manage the barriers to achieve its strategic objectives and enhance the value of services it provides to the community.
2.2This Risk Management Strategy incorporates and: promotes a common understanding of risk; outlines roles and responsibilities across the Council; proposes a methodology that identifies and manages risk in accordance with best practice thereby seeking to prevent injury, damage, loss and reducing the cost of risk.
2.3The Strategy is reviewed annually to ensure that it remains up to date and continues to reflect the Council’s approach to risk management. 2.4 The Corporate Risk Register, which accompanies the strategy, ensures that all relevant key risks are recorded and this is reviewed every six months by both management and Members.
2.5The last six monthly review of the Corporate Risk Register was discussed at Cabinet on 21 November 2017. Cabinet approved all amendments made to the risk register including a change to the risk rating of Transformation from C2 to B2, and the inclusion of three additional risks; Successful delivery of the corporate transformation programme; Homelessness and Alternative service delivery models. Cabinet also agreed to include more detailed updates on the progress of actions to mitigate risk from January 2018.
2.6The Cabinet noted the comments of the Business Support Overview and Scrutiny Committee on 26 October 2017 where officers undertook to look into a request that the narrative on the alternative delivery model risk should include more detail about concerns previously raised at the Committee regarding TUPE and pensions risks.
2.7At Business Support Overview and Scrutiny Committee on 30 November 2017 it was agreed that the capacity of the voluntary sector (VCS) in Medway would be assessed through the next six monthly review of the Corporate Risk Register. Discussions at the Strategic Risk Management Group and Corporate Management Team concluded that there is positive work underway to engage with the VCS, including through the implementation of the Three Conversations Model in social care, the forthcoming Overview and Scrutiny review of social isolation and the upcoming tender for VCS by Partnership Commissioning; as such this was not considered to be a significant corporate risk for inclusion in the Corporate Risk Register. A further report on this was presented to the Business Support Overview and Scrutiny Committee on 12 April 2018.
2.8On 10 April, the Cabinet considered a referral from the Health and Adult Social Care Overview and Scrutiny Committee held on 15 March 2018 in relation to the future of the RVS Older People’s Centre.
2.9The Cabinet noted the progress made with RVS in covering a matching grant to cover costs over the 12 month period 2018-2019.
2.10The Cabinet agreed that Medway Council officers and other interested parties work with RVS in the preparation of a sustainable programme for RVS Medway (Decision no. 50/2018 refers).
2.11The Cabinet agreed that a progress report be prepared and presented to Cabinet within 6 months (Decision no, 51/2018 refers).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.