Resolved
The Committee agreed to note the report.
Business Support Overview and Scrutiny Committee agreed this item on Thursday 5 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note the report.
2.1The Transformation programme is a 3 year programme running from 2016 to 2019. A total capital budget of £6m is being invested into the transformation programme to deliver £7m revenue savings over the following years:
2016/17 £0.430m 2017/18 £1.570m 2018/19 £5.000m
2.2There is a high degree of certainty that the savings will be achieved as base budgets are being reduced accordingly.
2.3The Transformation team are working with Assistant Directors and Service Managers to assist them with the identification of transformation projects and are supporting with the implementation where appropriate. 2.4 A full update on the transformation programme is attached at Appendix 1.
3. Advice and analysis
Diversity Impact Assessments are carried out for individual transformation projects where appropriate.
4.1The Delivery Managers and Programme Leads within the transformation team manage the risks and issues within their individual projects but must escalate any risks or issues that could threaten the programme to the Programme Manager who will determine an appropriate response or escalate the risk or issue to the Senior Responsible Officer.
Action to avoid or Risk Description Risk mitigate risk rating
Savings targets Transformation projects do not The transformation not achieved achieve the required savings programme is being D2 targets, which will put pressure closely managed on revenue budgets with all risks and issues being escalated through the appropriate channels to be dealt with
5.1Consultation will be carried out for each project where required. All Council guidelines, policies and procedures will be followed, including HR guidance on projects affecting staff.
6.1The transformation programme has dedicated financial support with an accountant working within the transformation team. Financial updates are reported to the transformation board.
6.2Since 2016/17 the transformation programme costing £6m over three years is budgeted to save a net £7m per annum from the Council’s revenue budget. It is forecast to achieve that.
7.1Any transformation projects that have legal implications will be passed to the legal department for specialist advice before being taken forward for action. 8. Recommendation
8.1Members are asked to consider this report and the transformation update report (Appendix 1).
Lead officer contact
Carrie McKenzie, Assistant Director – Transformation Gun Wharf, Dock Road, Chatham, Kent, ME4 4TR Tel: 333524 Email: [email protected]
Appendix 1 - Transformation Update – June 18
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Transformation Update: June 2018Appendix 1 | 142 KB | Download |
PDF |
Transformation Programme UpdateReport | 103 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.