The Cabinet noted the comments made by the Audit Committee on 27 June 2018, detailed in Section 7 of the main report. 93/2018 The Cabinet considered the proposed changes to the Contract Procedure Rules as set out in Appendix 1 to the main report, and the minor changes in revised page 4.99 as set out in Appendix 1 to the addendum report and recommended them to Full Council for approval. Reasons: These proposed changes will implement a more robust suite of Contract Procedure Rules.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
The report details proposed changes to the Contract Procedure Rules (CPRs). The proposed changes will provide greater efficiencies on procurement activities within the authority by establishing a uniform means to award lower value (under £25,000) contracts. There is also a definition of High, Medium and Low risk procurements and there is clarification on the requirement to use internal resources first.
The report was presented to the Audit Committee on 27 June 2018 and its comments are set out in Section 7 of the report. This report will be submitted to Full Council on 19 July 2018.
1. Budget and Policy Framework
1.1The Contract Procedure Rules form part of the Council’s Constitution, therefore, final approval of these Rules is a matter for Full Council. In addition, the Audit Committee’s terms of reference require it to consider any proposals for changes to codes of practice on tenders and contracts. The Audit Committee considered this report at its meeting on 27 June 2018 and the outcome of the discussion is detailed at section 7 of the report. This report will be submitted to Full Council on 19 July 2018.
Background
2.1The Council’s Contract Procedure Rules define the rules and processes to follow when spending Council budgets. The last review was approved in 2015 when the legislation, which governs public sector procurement (The Public Contracts Regulations 2015), was updated.
2.2It is best practice to keep the Contract Procedure Rules under periodic review. Within the most recent review, an opportunity was seen to clarify High, Medium and Low risk procurements, revise the procurement process for projects valued between £5,000 and £24,999 and clearly outline how internal resources should be engaged first before engaging any external consultancy support. 3. Options
3.1It is important that the Council implements and continuously reviews effective procurement practices. The options relating to this report are as follows:
Do nothing – the option of doing nothing would result in the same set of Contract Procedure Rules being used. The risk of this is the Contract Procedure Rules would not allow the efficiencies identified and would not be as clear as the new proposed wording.
Implement changes – the changes proposed will allow the Category Management team to proactively manage and resource higher value and risk based procurements. Officers will be clear when they should use internal resources.
4. Advice and analysis
4.1The three main changes are outlined below.
4.1.1 A new procurement level will be introduced. At present expenditure in excess of £5,000 is made through the Category Management Team and anything below this figure remains a responsibility of the service area. The new level will see this figure rise to £25,000. This increase will enable the Category Management team to proactively manage and resource higher value (i.e. over £25,000) and higher risk procurements.
4.1.1.1 It should be noted that £25k has been chosen as the new threshold since any expenditure over this value must be published on Contracts Finder (an advertising website for all public sector contracts) and also brings our procurement processes in line with other local authorities.
4.1.1.2 Whilst increasing the threshold for devolved procurement activity, it should be noted that the Category Management team will retain an oversight of all procurement activity. This includes the introduction of a “low value quotation form” which will be available on the Kent Business Portal (the Council’s chosen e-procurement website).
4.1.2 A definition of High, Medium and Low risk procurements will be introduced. This definition will improve the decision making process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.