102/2018 The Cabinet noted the progress made against the Procurement Strategy 2016-21 and agreed the suggested changes to the 2016-21 detailed in Appendix 1 to the report. Reasons: The updated Strategy will include amended and new objectives which will develop upon the strategic targets of those they replace.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
The purpose of this report is to update the Cabinet on progress made against the Procurement Strategy 2016-21. Amended and additional objectives are suggested within Appendix 1 for approval.
The Business Support Overview and Scrutiny Committee considered the draft Strategy at its meeting on 5 July 2018 and its comments are detailed in section 5 of the report.
1. Budget and policy framework
1.1The Council spends in excess of £230 million each year, which is a mixture of revenue funds and capital/grant monies. It is managed through various forms of procurement and undertaken centrally by the Category Management team. These procurements are approved by Cabinet or under officer delegation in accordance with the Council’s Contract Procedure Rules, which in turn form part of the Council’s constitution. Approval of the Procurement Strategy is a matter for Cabinet.
1.2The Category Management team, since its inception, has been successful at delivering benefits back to the Council as demonstrated by the graph below. The team has delivered benefits worth in excess of £51m back to the Council.
1.3The graph below illustrates the savings from ‘revenue’ and ‘non-revenue’ budgets. The annual fluctuations in the graph are due to; (1) the cyclical nature of procurements, (2) the reactive needs of services, (3) the resources available to deliver all projects in a particular financial year, (4) when the savings can be realised. 2. Background
2.1The 2016–2021 Procurement Strategy was launched to ensure that we improve on the previous strategy and continue to make Medway Council a great Council to do business with. As part of the new Strategy, 22 ‘objectives’ across the following five key strands were originally set:
Supporting the local economy Reducing red tape Improved services, better outcomes Intelligent spending Sustainable Procurement
2.2Of the original 22 objectives, it is suggest that 4 are replaced with revised objectives (as illustrated as struck through lines in Appendix 1 of the report). Revised objectives develop upon the strategic target of those they replace. There is also one additional target suggested.
2.3Below is a summary of our progress against those objectives to date:
18 objectives have been completed (Green) 5 objectives are on target to be fulfilled. (Amber). 0 objectives cannot be achieved. (Red)
2.3.1 The following proposed changes to the Strategy are set out below for the reasons set out in paragraphs 3.3 and 3.4:
4 objectives are proposed for removal (1, 2, 16 and 22) 4 new objectives are proposed to replace those formerly removed (1A, 2A, 16A and 22A) 1 new objective is being proposed (3A) – this develops on the work the team has conducted regarding Social Value.
2.4Appendix 1 sets out detailed performance against each of the objectives. Most notably:
The Council continues to engage with local suppliers and Small and Medium sized Enterprises (SMEs) at an impressive rate. We have continued the reduction of the administrative burden on local suppliers and SMEs via standardising our tender documents. We have met and engaged with the voluntary sector to help them be more successful in tender opportunities. The Category Management team is working closely with the Finance team to minimise unnecessary spend. We have created Frameworks which reduce time for delivery and are being used by other public bodies who pay to use them. This in turn creates a financial income for the Council.
3. Advice and analysis
3.1Medway has a local economy of £2.8 billion which is formed of some large businesses and approximately 13,000 small and medium sized businesses. Medway Council’s spend is therefore representative of approximately 10% of the local economy.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.