Resolved
The Committee agreed to note the report.
Business Support Overview and Scrutiny Committee agreed this item on Thursday 31 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note the report.
This covering report represents a review of the performance of the Joint Venture from the perspective of the Council client for first six months of the 2018/19 financial year. It is accompanied by an update on the Joint Venture’s achievements and financial performance prepared by the Partnership Director.
1. Budget and Policy Framework
1.1Review of the performance and financial position of the joint venture is a matter of Cabinet and there is a requirement to submit reports to Cabinet on a six monthly basis.
1.2The Business Support O&S Committee has responsibility for scrutinising Medway Norse.
2.1In March 2013 Cabinet agreed for the joint venture company, Medway Norse, to be established for the provision of facilities management (FM) services from 1 June 2013. It was established to:
Provide services to the Council more efficiently, giving better value for money; Grow the business through taking on external contracts; Increase employment opportunities for local people.
2.2In 2014 the joint venture also took on responsibility for the grounds maintenance contract and for an initial phase of school transport for children with special educational needs attending three schools (now five). At its meeting on 6 March 2018, Cabinet agreed to transfer the waste collection and street cleansing activities to Medway Norse from October 2019, which will take the joint venture’s gross turnover up to over £25million per annum.
3. Governance
3.1The Company’s Board of Directors comprises three representatives from Norse Commercial Services and two from the Council. The Council has two representatives, an elected member and Chair of the Board (Councillor Turpin) and Ruth Du-Lieu, Assistant Director Frontline Services. The Board is responsible for the overall performance of the joint venture.
3.2There is also an Operational Liaison Board, which consists of representatives from Medway Norse and nine representatives from the Council.
3.3Responsibility for the Corporate Client lies within a number of areas. The original core contract responsibility sits with Rob Dennis, Head of Corporate Projects, whilst the greenspaces and environmental elements are managed by Sarah Valdus, Head of Environment.
3.4The format of the regular update reports has been changed and, since the December 2018 meeting of the Cabinet, will take the form of a covering report from the Council’s corporate client, accompanied by update on the Joint Venture’s achievements and financial performance prepared by Andrew Mann, the Partnership Director at Medway Norse. As mentioned in the last progress report to this Committee in July 2018, a “balanced score-card” of performance indicators has been included in the update report at Appendix 1.
4. Facilities Core Contract
4.1The Head of Corporate Projects, together with colleagues from Medway Norse, meet and liaise closely with managers across all of the Council’s operational buildings, in order to fully understand service needs and to establish an effective working relationship. The actions arising from these meetings continue to form the basis for prioritising building repairs and maintenance budgets.
4.2The BRMF Funding strategy, has followed the requirements of Property Board in first commissioning condition reports in order to prioritise areas most in need of maintenance, phasing the overall programme to fit the funding available
4.3The plans prepared from this work are considered and agreed by the Corporate Strategic Property Board, chaired by Councillor Gulvin, and there is a comprehensive plan of works agreed for 2018/19, which amounts to around £500,000 with major works planned for the Central Theatre, Medway Park, Strood Sports Centre and Rochester Adult Education Centre.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 1.1 MB | Download |
PDF |
Medway Norse UpdateReport | 146 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.