Resolved
The Committee agreed to note the external auditor’s grant claims and returns certification report for 2017/18, as set out at Appendix 1 to the report.
Audit Committee agreed this item on Thursday 21 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note the external auditor’s grant claims and returns certification report for 2017/18, as set out at Appendix 1 to the report.
This report and appendix presents the work carried out by BDO, the Council’s external auditor for 2017/18, in respect of the certification of grant claims for the financial year ended 31 March 2018. The report is presented to the Audit Committee to comply with governance requirements.
1. Budget and Policy Framework
1.1In accordance with the terms of reference of the Audit Committee, receipt of the grant claim audit report is a matter for this Committee.
2.1BDO, as the Council’s external auditor for 2017/18, provides a certificate on the accuracy of grant claims and returns to various government departments and other agencies. The firm act as agents of Public Sector Audit Appointments Limited (PSSA) in respect of the annual Housing Benefit Subsidy Claim. Assurance reviews are also undertaken outside of the PSSA regime in respect of the Pooling of Housing Capital Receipts Return and the Teachers Pensions Return.
2.2The total value of these returns for the financial year 2017/2018 was £103m, comprising income of £96m of income and outgoings of £7m.
2.3A high level summary of the findings is set out in the following sections.
3. Housing Benefit Subsidy Claim
3.1BDO certify the value of the subsidy claim using methodology and sample sizes prescribed by PSSA and Department for Work and Pensions (DWP).
3.2No errors were identified in the initial sample of 60 claims tested. In accordance with PSSA guidance, additional testing was undertaken as a follow-up to issues reported in prior years, which did identify a number of errors. On completion of the additional testing, BDO issued a qualified audit certificate and quantified the effect of the errors identified on the Council’s entitlement to subsidy (based on extrapolations) in a letter to the DWP. If DWP decides to adjust the subsidy claimed by the value of the extrapolated errors the Council will have under claimed subsidy by a net value of £39,779. A summary of the audit findings is given below:
Non HRA Rent Rebates – The Council overstated the amount of expenditure above the cap limits by £818. If the DWP decided to adjust for this subsidy receivable would increase by £818.
Non-HRA Rent Rebates – The testing of the 2017/18 claim identified one case where an overpayment was misclassified and this year as the cell population is below 100, in accordance with DWP guidance, 100% testing was carried out. The auditors found an overstatement of Eligible overpayments of £4,158 and understatements of Technical overpayments of £2,466 and LA error and administrative delay overpayments of £1,692. As the entire cell population had been tested, the claim was amended accordingly.
Rent Rebates – Based on their testing and extrapolation, the auditors estimate an overstatement of eligible overpayments of £5,458, understatement of technical overpayment of £5,025 and understated HRA rent rebate expenditure by £433. If DWP decided to adjust for the extrapolated error, this would increase the subsidy receivable by £3,275.
Rent Allowances – Earned Income– Based on their testing and extrapolation, the value of errors are estimated as overstated benefit expenditure of £47,102 and a corresponding understated LA error and administrative delay overpayment claim of £47,012. These errors will not affect the subsidy receivable as the council are below the threshold for LA error.
Rent Allowances – Eligible Overpayments – Based on the extrapolation of the errors identified, it is estimated that the Council overstated the amount of eligible overpayments by £59,477 and understated LA error and administrative delay overpayments by £49,069 and LHA expenditure by £10,408. If the DWP decide to adjust for the extrapolated error subsidy would increase by £35,686.
4. Pooling of Housing Capital Receipts Return
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 217 KB | Download |
PDF |
External Audit Grant Claim ReportReport | 150 KB | DownloadRead as text |
Follow Audit Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Internal Audit Strategy 2025-28 Progress UpdateThe Committee noted the progress during 2025-26 against the Internal Audit Strategy 2025-28. | Noted | Open |
| 30 Jul 2026 | National Fraud Initiative Exercise - Annual UpdateThe Committee noted the report. | Noted | Open |
| 30 Jul 2026 | Audit Committee - Review of Terms of ReferenceThe Committee approved the suggested changes to Terms of Reference and provide a recommendation to Full Council for a... | Approved | Open |
| 30 Jul 2026 | Exclusion of the press and publicThe Committee agreed not to exclude the press and public and defer the item to the following meeting. | Agreed | Open |
| 19 Mar 2026 | Internal Audit Update 1 December 2025 to 28 February 2026The Committee noted the outputs and performance against the Internal Audit Plans for Medway for the period 1 December... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.