69/2019 The Cabinet noted the comments of the Business Support Overview and Scrutiny Committee as set out in section 5 of the report and approved the Corporate Risk Register set out at Appendix 1 to the report. The Cabinet noted that from 2019/20, updates to the Corporate Risk Register will be produced every quarter. Reasons: The establishment of a corporate framework for risk management is recommended by CIPFA and SOLACE and will complement and support the work already being carried out within each directorate to manage risks.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
CABINET 11 JUNE 2019 SIX MONTHLY REVIEW OF THE CORPORATE RISK REGISTER Portfolio Holder: Councillor Rupert Turpin, Business Management
Report from: Phil Watts, Chief Finance Officer and Chair of Strategic Risk Management Group
Author: Katey Durkin, Head of Finance Strategy
Summary In accordance with the Council’s Risk Management Strategy, this report presents the latest six monthly review of the Corporate Risk Register. This report was considered by the Business Support Overview and Scrutiny Committee on 4 April 2019. The comments of this Committee are set out in section 5 of the report.
1. Budget and Policy Framework
1.1The Cabinet as a whole has responsibility to ensure the effective operation of risk management in the Council. 2. Background
2.1Risk management is a process which aims to help the Council understand, evaluate and take action on all their risks. It supports effective decision making, identification of priorities and objectives and increases the probability of success by making the most of opportunities and reducing the likelihood of failure.
2.2Risk management is an integral part of good governance. The Council recognises that it has a responsibility to identify and manage the barriers to achieve its strategic objectives and enhance the value of services it provides to the community. The Council’s Risk Management Strategy incorporates and:
promotes a common understanding of risk; outlines roles and responsibilities across the Council; proposes a methodology that identifies and manages risk in accordance with best practice thereby seeking to prevent injury, damage and loss.
2.3The Corporate Risk Register, which accompanies the Strategy, ensures that all relevant key risks are recorded and this is currently reviewed and managed every six months by both management and Members. 3 Advice and analysis
3.1On 20 November 2018, Cabinet reviewed the last six monthly update of the Corporate Risk Register, the first presented in the new template, and agreed the recommendation from Business Support Overview and Scrutiny Committee to add the risk of Cybersecurity to the Corporate Risk Register.
3.2Risk owners have reviewed and updated their risks with the revised register presented at Appendix 1 to this report. No risks are proposed to be removed through this review, however this register includes the new Cyber security risk prepared in response to the Cabinet decision; this is presented as SR37 in Appendix 1.
3.3Following a recommendation from the Regeneration, Culture, Environment and Transformation Directorate Management Team, the Strategic Risk Management Group and Corporate Management Team have also reviewed a new risk on the Transfer of the Council’s Waste Contract to Medway Norse; this is presented as SR38 in Appendix 1.
3.4At present, Council Plan performance monitoring and the Revenue and Capital Budget monitoring reports are all produced on a quarterly basis, while the updates of the Corporate Risk Register are currently only produced every six months. It is proposed that to facilitate understanding of the Council’s performance in the round and to support decision making, from 2019/20, updates of the corporate risk register will be brought into line with the performance and budget monitoring reports, being produced and reported on a quarterly basis.
4 Consultation 4.1 Updates to the Corporate Risk Register have been provided by risk owners and the revised register has been discussed with the Strategic Risk Management Group and Corporate Management Team. Members are being consulted with both via the Business Support Overview and Scrutiny Committee and Cabinet in June 2019.
5. Business Support Overview and Scrutiny Committee – 4 April 2019
5.1Members considered a report regarding the 6 monthly review of the Council’s Corporate Risk Register.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.