The Council agreed to add the schemes set out in sections 3 to 11 of the report to the Capital Programme, approve the virement as set out in section 12 of the report and to remove £850,000 from the Revenue Budget as set out in section 11.2 of the report.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1Council approved the capital programme for 2019/20 and beyond of £295.867million at its meeting on 21 February 2019.
2.2Several further schemes and proposals have been identified which would require spending over and above that previously agreed and a number of other amendments to the programme are now required. At its meetings on 6 August 2019 and 19 November 2019, the Cabinet recommended the following amendments to the programme for approval by Full Council:
3. Family Hubs and Wellbeing Centre
3.1The Round 1 Capital Budget Monitoring report was considered by Cabinet on 6 August, and reported an overspend of £8,000 on the Family Hubs and Wellbeing Center programme. Funding has been identified to meet this pressure, primarily Section 106 contributions, and Cabinet recommended that Council agree the additions to the Capital Programme to fund this overspend.
4. Medway Growth
4.1As the ‘Medway Growth’ scheme, under a joint venture with Norse Property Services, will not now proceed, the Council will not incur this expenditure and will no longer need to borrow the £1.339 million funding. Therefore, Cabinet, on 6 August, recommended to Council that this scheme be deleted from the capital programme.
5. Mercury Abatement
5.1The Round 2 Capital Budget Monitoring report was considered by Cabinet on 19 November, and reported that Mercury abatement works to the Medway Crematorium overspent by £102,259 as additional concreting works were required to the base. It has not been possible to identify additional funding or a suitable virement, and therefore Cabinet recommended to Full Council to increase the budget, funded from further borrowing.
6. Command of the Heights
6.1The Landscaping works to provide new public realm on Chatham Riverside through the Command of the Heights project have identified archaeological remains, which have caused delays and additional works, resulting in an overspend of £397,259. Further grant funding has been secured through the Heritage Lottery Fund to finance a significant element of this overspend; the work associated with the Casements. The balance will be secured from Great Lines Heritage Park Section 106 contributions and a contribution from the Greenspaces Development revenue budget. Cabinet, on 19 November, recommended to Full Council to increase the budget to include this funding.
7. Rochester Station Totem
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of the Council's Petitions Schemea) The Council noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.