This report details contracts awarded in accordance with the provisions of the current Contract Procedure Rule 1.8.2.
Exemptions to Contract Procedure Rules, to deal with the letting of contracts in exceptional circumstances where it is considered to be in the best interests of the Council to do so, can be approved by the Monitoring Officer, provided that the exemption does not breach any EU or UK Directive, Statute or Regulation.
1. Budget and Policy Framework
1.1The constitution requires that the Monitoring Officer reports to Council the number of contracts recommended by Directors for award and approved by the Monitoring Officer under delegated powers and reliance on the exceptional circumstances, permitted by Contract Procedure Rules 1.8.2.
2. Background 2.1 In accordance with Sections 1.8.2.1 and 1.8.2.2, individual provisions within the Contract Procedure Rules may be exempted in exceptional circumstances, where it is considered to be in the interests of the Council to do so, provided that the exemption does not breach any EU or UK Directive, Statute or Regulation.
2.2The Monitoring Officer, further to requests from Directors, has approved 6 exemption requests since the matter was last reported to Council on 23 January 2020.
2.3The Monitoring Officer can sign exemptions off up to the relevant financial value as set within the Procurement Directives. Exceeding this threshold would result in the requirement being subject to the Public Contracts Regulations 2015. For the year this report covers, these values are as follows:
2.3.1 Good and services: £181,302
2.3.2 Works £4,551,413
3. Exemptions Granted
3.1The Exemptions granted during 2020 were as follows:
Exemption 1 – Rochester Riverside School
Value: £1.6m (Works contract)
Project Summary: • Through the Rochester Riverside development, an obligation was put on the contractor to deliver a 1FE (One Form of Entry) school with 2FE facilities for future expansion. • The DfE during the term of the original contract awarded Medway Council £1.6m on the proviso that Medway engaged with and took responsibility of the delivery.
Rationale: • To save time on the project and remove any disruption for the school. • To remove any funding responsibility from the Council. • To acquire a 2FE school without the need to source funding in the future. • Provide continuity of the project by utilising the same contractor. • Enables a consistency of the build fabric and visual impact by having the one professional team on board.
Directorate seeking Exemption Request: Children and Adults
Date Exemption Approved by the Monitoring Officer: September 2020
Project Summary: • To deliver an EIA scoping report for the rail and road elements of the project.
Rationale: • A consultant with prior knowledge of the site and scheme was needed to urgently address various services. • Delaying the appointment of a consultant could have incurred additional project delays and cost. • The use of the existing consultant would have reduced planning risk and demonstrated consistency in the approach.
Directorate seeking Exemption Request: RCET
Date Exemption Approved by the Monitoring Officer: August 2020
Exemption 3 – Social Care Recruitment Branding
Value: £36k (Services contract)
Project Summary: • An Ofsted inspection identified permanency of staffing as an area of improvement. • The project was to deliver revised branding for such recruitment purposes.
Rationale: • The supplier had a successful track record with other public bodies and was able to mobilize in time.
Directorate seeking Exemption Request: Children and Adults
Date Exemption Approved by the Monitoring Officer: September 2020
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of the Council's Petitions Schemea) The Council noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.