Resolved
The Committee agreed to note the updated Audit Plan for 2020/21 including the variation to the core fees from 2019/20 and those proposed for both the core fees and other audit services for 2020/21.
Audit Committee agreed this item on Thursday 17 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note the updated Audit Plan for 2020/21 including the variation to the core fees from 2019/20 and those proposed for both the core fees and other audit services for 2020/21.
2.1In accordance with the International Standards on Auditing this report communicates the updated annual audit plan for 2020/21. The purpose of the updated audit plan is to provide an update to communicate the Group materiality and the strategy in relation to Group accounts.
2.2The proposed fee for the audit is £190,087, which is an increase of £6,746 over that levied for 2019/20. Any fee in addition to the scale fee of £109,687 will need to be agreed by both the Chief Finance Officer and the Public Sector Audit Appointments (PSAA).
2.3The plan also sets out the external auditors’ approach to: - Group audit scope and risk assessment - Significant and other risks identified, - Accounting estimated and related disclosures, - Other matters, - Progress against prior year recommendations,
Revised April 2020 - Materiality, - Value for Money arrangements, - Audit logistics and team, - Audit fees, and - Independence & non audit services.
2.4The Updated Audit Plan for the year ending 31 March 2021 is attached as Appendix 1 of this report.
2.5The Audit Scale Fee for 2020/21 remains as set via the contract tendering process undertaken by PSAA on behalf of c98% of all local authorities. Page 27 of the Plan details a proposed variation to the original scale fee of £109,687.
2.6For the audit of 2019/20 an additional fee of £73,654 was agreed by the PSAA on 01 March 2022.
2.7For 2020/21 the proposal is an additional variance of £80,400, taking the fee to £190,087. This assumes non-covid additional costs from 2019/20 all remain, and also takes account of the following: - Additional VFM work required under the new NAO Code, - Increased audit requirements of the revised International Standards of Auditing, - The introduction of group accounts, and - The complexity of audit.
2.8Whilst it is acknowledged that the regulatory landscape has changed around local authority audit and other factors have resulted in additional pressure on audit firms, the final audit fee remains to be agreed by the Chief Finance Officer, subject to discussion regarding the actual additional work required and the reasons why. The proposed additional fees are also subject to approval by PSAA in line with the Terms of Appointment.
2.9The proposed fees for other services, detailed on page 28 of the Plan will increase compared with those agreed for 2019/20 with the Chief Finance Officer as follows: - Certification of Housing Benefits subsidy claim - £29,750 (£20,000 in 2019/20), - Certification of Pooling of Housing Capital Receipts - £7,500 (£5,000 in 2019/20), - Agreed upon procedures engagement relating to the Teachers’ Pensions End of Year Certificate - £6,000 (£5,000 in 2019/20).
Revised April 2020 3. Risk management
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
App 1 Audit Plan Update for the Year Ending 31 March 2021Appendix | 5.2 MB | Download |
PDF |
Audit Plan Update for the Year Ending 31 March 2021Report | 162 KB | DownloadRead as text |
Follow Audit Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Internal Audit Strategy 2025-28 Progress UpdateThe Committee noted the progress during 2025-26 against the Internal Audit Strategy 2025-28. | Noted | Open |
| 30 Jul 2026 | National Fraud Initiative Exercise - Annual UpdateThe Committee noted the report. | Noted | Open |
| 30 Jul 2026 | Audit Committee - Review of Terms of ReferenceThe Committee approved the suggested changes to Terms of Reference and provide a recommendation to Full Council for a... | Approved | Open |
| 30 Jul 2026 | Exclusion of the press and publicThe Committee agreed not to exclude the press and public and defer the item to the following meeting. | Agreed | Open |
| 19 Mar 2026 | Internal Audit Update 1 December 2025 to 28 February 2026The Committee noted the outputs and performance against the Internal Audit Plans for Medway for the period 1 December... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.