35/2023 The Cabinet approved the removal of the collapsed section of Rochester Pier and timber dolphins, as set out at option 2 within the report, in order to remove the potential hazard to navigation and provide a cleared location for future restoration of the pier. 36/2023 The Cabinet recommended Full Council to approve the addition of £137,172 to the Capital Programme to be funded by borrowing. Reasons: Removal of the collapsed pier sections and timber dolphins from the river will negate risk of debris becoming a danger to navigation and thereby mitigate risks of compensation claims of damage to vessels and private river infrastructure. Clearance of the collapsed sections of the pier and dolphins will also provide a significantly improved starting point for future restoration works and sustaining navigational safety, thereby increasing the opportunities for a volunteer led Trust to take on the management and maintenance of Rochester Pier.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
ROCHESTER PIER SALVAGE Portfolio Holder: Councillor Adrian Gulvin, Portfolio Holder for Resources
Report from: Richard Hicks, Director of Place and Deputy Chief Executive
Author: Adam Taylor, Senior Engineer
Summary In 2019 Rochester Pier closed owing to structural safety concerns relating to the central floatation platform linking the two brows from the upper section of pier to the pontoon. This report seeks approval to remove the collapsed sections of the pier and timber dolphins from the riverbed.
Within the relevant lease, the pier is described as Esplanade Pier, for the purposes of this report, Rochester Pier is the term used.
1. Budget and policy framework 1.1. Cabinet is asked to agree to the removal of collapsed sections of the pier to aid future restoration and removal of two timber dolphins to prevent navigation hazard. Adding the required funding to carry out these works however, is a matter for full Council.
1.2The recommendations in this report support the priorities outlined in Medway’s Council Plan 2022 – 2023, specifically putting ‘Medway on the map’. By building on what makes Medway unique - the river, our heritage and sporting legacy - Medway on the Map promotes our area as a great place to live, work, learn and visit’.
2. Background 2.1. Rochester Pier, originally constructed in 1881 and known as Esplanade Pier, was built to provide river trips and passenger services. In 1998 the pier was extensively improved with a new 19m long pontoon to accommodate the Kingswear Castle paddle streamer, a roof on the T section and pedestrian access via a link span of two brows with central flotation platform.
2.2A Marine Survey in April 2019 identified eleven immediate priority repairs, including the removal of two redundant timber dolphins owing to risk of collapse into the river, causing navigational hazard and with the flotation platform showing signs of metal buckling. 2.3. In September 2019, support beams of the central platform began to crack, marine engineers advised pier closure and quoted £56k for essential repairs.
2.4With insufficient funding available, the river tour company ceased use of the pontoon and the pier was closed.
2.5Rochester Bridge Trust were approached for advice and potential funding contribution but were unable to provide charity funding to a Local Authority. However, they agreed to fund a feasibility report for the creation of a volunteer led Trust to obtain, manage and maintain Rochester Pier and to expand funding opportunities,
2.6In May 2022 the flotation platform failed, causing the two brows to collapse into the riverbed, causing damage to the pontoon and potential structural stress to the T section.
2.7In October 2022, three quotes were obtained for the removal of the collapsed sections of the pier and removal of the wooden dolphins. These were undertaken to enable officers to provide an estimate of the funding needed.
3. Options 3.1. Option 1 - part removal
3.1.1. Timber dolphins are considered more dangerous to navigation than collapsed brows. The removal and disposal of the dolphins is estimated to cost £27k.
3.1.2. Commissioning a marine structural assessment of the upper T section of the pier will be required and is estimated to cost £3,400.
3.1.3. If the assessment is undertaken and confirms the T section is safe for public use, the pier could be re-opened but with a recommendation to lock the mains gates between dawn and dusk.
3.2Option 2 - full removal of collapsed sections of the pier and timber dolphins
3.2.1. Carrying out all salvage works would consist of two brows, the central flotation platform, two wooden dolphins and associated debris being removed from the riverbed.
3.2.2. The required works would eliminate the undesirable view of pier wreckage from Rochester Castle, Rochester Bridge and Esplanade and the clearance of the collapsed sections of the pier and dolphins would provide an easier starting point for future restoration works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.