The Cabinet noted the outcome of consideration of the report by the Audit Committee, as set out at paragraph 4.1.6 to the report and the comments of the Business Support Overview and Scrutiny Committee, as set out in the addendum report. 49/2023 The Cabinet approved the 2023/24 Risk Strategy at Appendix 1 to the report, which set out the Council’s approach to risk management. 50/2023 The Cabinet agreed to delegate authority to the Chief Operating Officer, in consultation with the Portfolio Holder for Business Management, to consider adding to the Risk Strategy, references to resource risks, risk ratings and unexpected risks, as set out in paragraphs 1.9 to 1.11 of the Addendum report and if considered appropriate, to make the relevant changes to the Risk Strategy. Reasons: The establishment of a corporate framework for risk management is recommended by CIPFA and SOLACE and will complement and support the work already being carried out within each directorate to manage risks.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
In accordance with the Council’s Risk Management Strategy, this report presents the annual review of the Risk Strategy.
The report was considered by the Audit Committee on 16 March 2023. The Committee noted the report. The report is also due to be considered by the Business Support Overview and Scrutiny Committee on 30 March 2023, the comments of which will be set out in an addendum report.
1. Budget and Policy Framework
1.1Good corporate governance requires that local authorities identify all their significant strategic and operational risks and put effective risk management and internal control systems in place.
1.2In line with its terms of reference, the Audit Committee is responsible for providing independent assurance on the adequacy of the risk management framework and the associated control environment, including consideration of the Council’s approach to risk management.
1.3The Cabinet is responsible for ensuring the effective operation of risk management in the Council.
Background
2.1Risk management is a process which aims to help the Council understand, evaluate and act on all their risks. It supports effective decision making, identification of priorities and objectives and increases the probability of success by making the most of opportunities and reducing the likelihood of failure.
2.2Risk management is an integral part of good governance. The Council recognises that it has a responsibility to identify and manage the barriers to achieve its strategic objectives and enhance the value of services it provides to the community. The Council’s Risk Management Strategy incorporates and: promotes a common understanding of risk. outlines roles and responsibilities across the Council. proposes a methodology that identifies and manages risk in accordance with best practice thereby seeking to prevent injury, damage and loss.
3. Advice and analysis
3.1The Risk Strategy is reviewed annually to ensure that it remains up to date and continues to reflect the Council’s approach to risk management. The 2023/24 Risk Strategy is shown in Appendix 1. The current 2022/23 Risk Strategy is shown in Appendix 2 for reference.
Consultation
4.1Following consultation with Corporate Management Team (CMT), the following have been reflected in the 2023/24 Risk Strategy:
4.1.1. The disbandment of the Strategic Risk Management Group (SRMG). The leadership and support for risk management remains with CMT.
4.1.2. Strategic risks are distinguished as follows:
Live risks require continued management and further mitigating action. These risks may change each quarter. Managed risks are risks where all reasonable mitigation has been applied and embedded into business-as-usual work. Due to their nature or sensitivity, these risks may still require a corporate overview but would not typically change each quarter.
4.1.3. Increased emphasis of the different levels of risk register to ensure risks can be escalated up and managed down appropriately. Risk registers will be held at service, project/programme, directorate, and strategic level.
4.1.4. A simplified 4x4 risk matrix together with scoring criteria to enable more accurate and informed risk evaluation.
4.1.5. A revised tolerance level of BI which reflects the simplified risk matrix whilst maintaining the framework for escalating the most severe risks.
4.1.6. The Audit Committee noted this report at its meeting on 16 March 2023. 5. Financial, legal and risk implications
5.1There are no financial or legal implications arising from the review of the Risk Strategy.
Recommendations
6.1The Cabinet is asked to note the outcome of consideration of the report by the Audit Committee, as set out at paragraph 4.1.6 to the report and the comments of the Business Support Overview and Scrutiny Committee, as set out in the addendum report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.