The Council agreed the following additions to the capital programme, as set out in sections 4 and 5 of the report: i) £430,000 to the capital programme to fund the overspend reported on the Operational Depot scheme, to be funded by Prudential Borrowing, and ii) £4,655 to the capital programme to fund the overspend on the Mountbatten House Purchase scheme, to be funded from borrowing in advance of the capital receipts expected from the sale of the building to Medway Development Company.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report requests Council approval for additions to the Capital Programme as recommended by Cabinet on 11 June 2024.
1. Recommendations 1.1. The Council is requested to agree the following additions to the capital programme, as set out in sections 4 and 5 of the report:
i) £430,000 to the capital programme to fund the overspend reported on the Operational Depot scheme, to be funded by Prudential Borrowing, and
ii) £4,655 to the capital programme to fund the overspend on the Mountbatten House Purchase scheme, to be funded from borrowing in advance of the capital receipts expected from the sale of the building to Medway Development Company.
2. Budget and policy framework 2.1. It is the responsibility of Cabinet to ensure that expenditure for each capital scheme remains within the budget approved by the Council but it remains the responsibility of Council to approve schemes for inclusion in the capital programme.
3. Background 3.1. Council approved the capital programme for 2023/24 and beyond on 23 February 2023. On 11 June 2024, the Cabinet received the Capital and Revenue Outturn and Annual Debt Write Off Report 2023/24 and recommended the amendments set out below for approval by Council. In addition, this report was considered and noted by the Business Support and Digital Overview and Scrutiny Committee on 20 June 2024. 4. Operational Depot Scheme 4.1. This was a scheme to acquire an operational depot site in Rochester. The following issues have arisen throughout the duration of the contract:
• Road closer delays in order to carry out power/ water supply to site as well as road safety works. • Further works around the large retaining wall across the site and the associated effects on site drainage, requiring re design. • Changes in material supplies e.g. cladding no longer available so alternative sought at significant increased costs due to the well-advertised changes in market conditions at the time. • Dispute and negotiations over the extension of time (EOT) claims from contractor.
4.2The anticipated overspend of £430,000 was reported via the monitoring throughout 2023/24 and a final amount has now been agreed with the contractor. The Cabinet, therefore, recommended to Council to add £430,000 to the capital programme, funded from prudential borrowing, to fund this overspend.
5. Mountbatten House Purchase Scheme 5.1. There is an overspend of £4,655 on the Mountbatten House Purchase scheme, due to ongoing costs in preparing the building for sale to Medway Development Company. The Cabinet, therefore, recommended to Council to add £4,655 to the capital programme, funded from prudential borrowing. The service will also be reporting to a future meeting of Cabinet seeking a further budget addition for ongoing costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of the Council's Petitions Schemea) The Council noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.