Item300
Resolved
a) The Committee noted the outputs and performance against the Internal Audit Plan Q1-Q2 for the period 1 April to 31 July 2025 as detailed at Appendix 1. b) The Committee agreed the revisions to the Internal Audit Plan Q1-Q2 2025-26, as detailed in section 8 of appendix 1. c) The Committee agreed that should significant progress not be made on the following Internal Audit review action, details of which will be reported back to the Audit Committee on 27 January 2026, as part of the Internal Update report, the Director of Place will be requested to attend the Audit Committee on 27 January 2026 to provide an update on progress: “The Tree Policy should be updated to include the council’s commitment to tackling climate change, recognising Norse as the council’s contractor and any other relevant changes”
Word for word from the decision Medway published for this meeting.
Source: democracy.medway.gov.uk