AI summaryMedway Cabinet approved delivery of the £1.5m Pride in Place Impact Fund capital grant programme, to be fully committed by 31 March 2027, with delegated authority to the Director of Place.
Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£1.5m capital grantFrom MHCLG Pride in Place Impact Fund, fully committed by 31 March 2027
What happens nextLaunch grants in early 2026Three workstreams scoped and ready to launch
Who it affectsMedway residents, businesses, town centresImprovements to community spaces, public spaces, high streets and town centres
What was decided
Cabinet approved delivery of the £1.5m Pride in Place Impact Fund capital grant programme to March 2027, in line with MHCLG timescales. Report P6
Cabinet delegated authority to the Director of Place, in consultation with the Portfolio Holder for Economic and Social Regeneration and Inward Investment, to deliver the programme. Report 1.2
Why
Approval enables delivery, benefitting Medway's residents, communities and businesses, in line with the Council's overarching regeneration priorities. Report P8
Any uncommitted spend by March 2027 would have to be returned to MHCLG, losing the opportunity to invest in high streets, town centres, community and public spaces. Report P8, 6.2
What happens next
Scoping of all three workstreams is underway, with grants to launch early 2026 and projects delivered by March 2027. Report 4.6, P39
First monitoring report to MHCLG due February 2026, covering measured outputs including facilities created or improved, commercial space, community, green and public realm space. Report 4.2, P14, P15, P16, P17, P18, P19
Decision panel to consider prioritised public realm projects for Gillingham and Chatham in January 2026, following December 2025 workshop with officers and stakeholders. Report 8.2, P30
The money
£1.5m Total Pride in Place Impact Fund capital grant from MHCLG Report P4, P6, 10.2
£300,000 Allocation for Shopfront Grant Scheme across Medway Report P24
£2,500 Smaller grant ceiling for cosmetic shopfront improvements such as repairs, repainting, signage and lighting Report P25
£5,000 Larger grant ceiling for structural works including accessibility enhancements Report P25
£800,000 Town centre public realm improvement package, co-created with stakeholders Report P28
£400,000 Partners in Investment scheme to leverage private sector investment in empty town centre properties Report P32
£20m Additional amount granted under PIPIF to pre-determined deprived neighbourhoods, which Medway did not receive
Options considered
Chosen: Approve delivery of PIPIF workstreams as set out in the report. Approval is recommended to meet the 31 March 2027 deadline and deliver benefits to residents, communities, businesses and town centres; work must begin at pace and scoping has commenced. Report P39
Rejected: Reject delivery of the PIPIF workstreams as set out in the report. Programme would be delayed, risking failure to meet the delivery timescale, and uncommitted spend would have to be returned to MHCLG, a significant loss to Medway. Report 5.2, 6.2
Implications
Financial: £1.5m will be added to the Capital Programme under the S151 Officer's delegation, as the funding is external, requires no Council contribution and is ring fenced; no impact on Council budget. Report 10.2, 10.3, 10.4
Financial: MHCLG will release 50% in 2025/26 and the remainder in 2026/27; first S151-signed reporting submission is due February 2026.
Financial: No revenue or capacity funding is available; the fund is 100% capital, with delivery and administration resourced from existing staff. Report 4.4
Legal: Legal team engaged to draft grant funding agreements including clawback provisions, subsidy control and procurement compliance; S151 Officer has signed a Section 50 MOU with MHCLG. Report P53, 11.2
Equalities: Delivery aligns with Medway 2041, embedding the Council's equality ethos; Diversity Impact Assessments are incorporated at key junctures to meet the Equalities Act 2010. Report 3.3
Climate: Climate change will be considered in delivery of each capital scheme, in line with the Council's target for Medway to be carbon neutral by 2050. Report P48
Risk: Risk register in development; key risks are failure to spend effectively, negative publicity from high expectations, lack of resource, and projects not delivering intended outputs, all rated CII. Report P42, P43, P44, P45
Staffing: Delivery will be resource intensive, predominantly from existing staff, requiring multidisciplinary working and support from legal, comms, digital, finance, audit and procurement. Report 4.4
Who and where
Medway residents, communities and local businesses Report P8
Owners and occupiers of commercial premises along shopping parades and town centres eligible for the Shopfront Grant Scheme Report P24, P25
Town centre users benefiting from public realm improvements in Gillingham and Chatham Report P28, P30
Private sector partners potentially investing in refurbished town centre empty properties through the Partners in Investment scheme Report P32
Council staff in Town Centre, Economic Development and Shared Prosperity Fund teams, facing significant additional delivery pressure Report 4.4, P44
Timeline
28 October 2025: Briefing presentation delivered to all three Medway MPs on PIPIF, receiving positive feedback and offers of ongoing support. Report 4.7
2 December 2025: Engagement workshop held in Gillingham, facilitated by BPTW, bringing 35 council officers and 33 external stakeholders together to prioritise public realm projects. Report 8.2, P29
January 2026: Cabinet decision to approve delivery and delegate authority; project ideas from the workshop to go to a decision panel for approval. Report 8.2
early 2026: Public realm improvements for Chatham to begin; grants to launch across all three workstreams. Report P30, 4.6
February 2026: First PIPIF monitoring and reporting submission to MHCLG, signed off by S151 Officer. Report 4.2
31 March 2027: Deadline by which all £1.5m PIPIF funding must be fully committed; uncommitted spend must be returned to MHCLG. Report P5, P8
Plain English for the jargon
PIPIF: Pride in Place Impact Fund, a Ministry of Housing, Communities and Local Government capital grant programme.
MHCLG: Ministry of Housing, Communities and Local Government, the UK government department providing the funding.
S151 Officer: The council officer with statutory responsibility for financial administration, who has signed the Memorandum of Understanding with MHCLG.
MOU: Memorandum of Understanding, the agreement signed by the S151 Officer to accept the £1.5m Section 50 non-ringfenced grant.
SELEP: South East Local Enterprise Partnership, with legacy funding streams identified as a possible source of additional revenue support.
MDC: Medway Development Company, supporting delivery of the Chatham public realm improvements.
BPTW: Consultants facilitating the December 2025 engagement workshop, building on prior work for the Gillingham Vision and Action Plan.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
04/2026 The Cabinet approved delivery of the £1.5m capital grant programme to March 2027, in line with Ministry of Housing Communities and Local Government timescales. 05/2026 The Cabinet delegated authority to the Director of Place in consultation with the Portfolio Holder for Economic and Social Regeneration and Inward Investment, to deliver the programme. Reasons: Approval of the programme will enable delivery, benefitting Medway’s residents, communities and businesses, in line with the Council’s overarching regeneration priorities. Any uncommitted spend by March 2027 will need to be returned to MHCLG, and the council would lose the PIPIF opportunity to invest in improvements to our high streets, town centres, community and public spaces.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Cabinet 13 January 2026 Pride In Place Impact Fund Portfolio Holder: Councillor Harinder Mahil, Portfolio Holder for Economic and Social Regeneration and Inward Investment
Report from: Adam Bryan, Director of Place
Author: Jessica Jagpal, Head of Place Strategy, Investment & Social Regeneration
Summary Medway Council has been allocated £1.5 million capital grant funding from the Pride in Place Impact Fund (PIPIF). Ministry of Housing Communities and Local Government (MHCLG) has set out three main priorities for the fund which include improvements to community spaces, public spaces, and high streets and town centres.
Funding must be fully committed by deadline 31 March 2027. This allows 14 months for delivery from January, if approved by Cabinet. This report seeks approval of the PIPIF delivery programme and requests delegated authority to the Director of Place, in consultation with the Portfolio Holder for Economic and Social Regeneration and Inward Investment accordingly.
1. Recommendations 1.1. The Cabinet is asked to approve delivery of the £1.5m Pride in Place Impact Fund (PIPIF) capital grant programme to March 2027, in line with Ministry of Housing Communities and Local Government timescales.
1.2The Cabinet is asked to delegate authority to the Director of Place in consultation with the Portfolio Holder for Economic and Social Regeneration and Inward Investment, to deliver the Pride in Place Impact Fund programme.
2. Suggested reasons for decisions 2.1. Approval of the PIPIF programme will enable delivery, benefitting Medway’s residents, communities and businesses, in line with the Council’s overarching Regeneration priorities. 2.2. Any uncommitted spend by March 2027 will need to be returned to MHCLG, and the Council would lose the PIPIF opportunity to invest in improvements to our high streets, town centres, community and public spaces.
3. Budget and policy framework 3.1. Delivery of the PIPIF programme is in line with the One Medway Council Plan priorities, particularly supporting clean, green, safe and connected communities, a growing economy and improving wellbeing for all.
3.2Delivery of the PIPIF programme is in line with the Council’s Town Centre Strategy and emerging Regeneration Strategy, Medway 2041.
3.3Medway 2041 embeds the Council’s ethos to eliminate unlawful discrimination, actively promote equality, growth for all, and foster good relations between communities, through improving quality of life and opportunities for everyone. Diversity Impact Assessments are incorporated at key junctures to ensure all requirements of the Equalities Act 2010 are satisfied.
4. Background 4.1. PIPIF was launched as part of Government’s Pride in Place Strategy initiatives. Medway did not receive the additional £20m granted to pre- determined deprived neighbourhoods. The overarching aim of PIPIF is rebuilding community pride in local areas and creating thriving places. Three main priority areas for the fund include improvements to community spaces, public spaces, and high streets and town centres.
4.2The fund requires regular monitoring with the first reporting submission in February 2026. Measured outputs include:
• number of facilities & premises created/improved;
• amount of commercial space created/improved sqm;
• amount of community/culture/sports/heritage space created/ improved sqm;
• amount of green/blue space created/improved sqm;
• amount of public realm created/improved sqm; and
• number of green retrofits to non-residential buildings/ facilities.
4.3PIPIF encourages local authorities to leverage additional funding where possible including any other Government or private sector funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.