CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Medway Council
Cabinet, Tuesday 10 March 2026 at 7.00pm

Gateway 1 Report: Supply, Installation, Maintenance and Operation of on-Street EV Charging Infrastructure

Agreed Executive 1 paper

AI summaryMedway Cabinet approves competitive procurement for on-street EV charging network, using £2.14m LEVI grant and a 15-year supplier-funded contract.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedOpen Procedure tender for on-street EV charging
Money£2.14m LEVI grantPlus £2m to £30m operator investment over 15 years
What happens nextTender issued 16 March 2026Final award approval targeted by 7 August 2026
Who it affectsResidents without off-street parkingAnd EV users across Medway

What was decided

The Cabinet agreed to pursue the procurement for the supply, installation, maintenance and operation of on-street EV charging infrastructure, under the preferred option 4 (competitive procurement) identified in paragraph 6.2.4. Report P68

An Open (single-stage) Procedure will be used, with a 15-year contract term and the option to extend for one year by mutual agreement. Report P71, P86

The contract will be a supplier-funded, concession-style model, with a single form of security (Parent Company Guarantee or Performance Bond) rather than both. Report 2.5, 2.6, P36

Why

Publicly accessible EV charging supports the transition away from petrol and diesel vehicles, particularly for residents without off-street parking, and helps meet Medway's climate change, air quality and highway authority duties. Report 2.1, 2.2, P29, P130

A competitive open procedure maximises market competition, transparency and value for money under the Public Contracts Regulations 2015, and the market is mature and competitive with several experienced operators. Report 2.4, P58, P59, P60

The supplier-funded model limits direct Council capital exposure, transferring most financial, operational and maintenance risk to the operator, and the £2.14m LEVI grant award places an expectation on the Council to progress delivery. Report 2.3, P112, P113, 3.8, 3.9

What happens next

Tender documents will be issued on 16 March 2026, with shortlisting to 5 suppliers by 8 June 2026, and evaluation of final bids completed by 7 August 2026 ahead of award approval. Report P75, P76, P77, P78, P79, P80, P81

Contract management will be led by the Head of Highways, with KPIs monitored quarterly and reported to RCE DMT, and final contracts subject to OZEV/Department for Transport sign-off under LEVI conditions. Report P52, P53, P55, 8.5

Future expansion to Council car parks, buildings or other Council-owned assets will need separate approval under the Council's financial and governance procedures. Report 2.7, 3.6, P45

The money

  • £2.14m LEVI external capital funding awarded to Medway Council for on-street EV charging Report 3.2, 3.8, 3.9
  • £2m to £30m Estimated total contract value over 15 years, representing operator commercial investment, not direct Council spend Report P112
  • £5.19M FTS threshold for works and concession services, above which this procurement falls Report P125

Options considered

  • Chosen: Option 4: Competitive procurement using an Open (single-stage) Procedure. Maximises market competition, secures best value and a scalable long-term model, transfers financial and operational risk to the operator, and aligns with LEVI expectations Report P68, P69, P70, P85
  • Rejected: Option 1: Do nothing. Would undermine climate, air quality and transport objectives, and risk losing the £2.14m LEVI funding benefit Report P66, P67
  • Rejected: Option 2: Use a framework or existing contract. Frameworks focus on supply and installation rather than the long-term concession-style model needed, and may limit commercial flexibility and competitive tension Report P67
  • Rejected: Option 5: Direct Council-funded delivery, limited pilot or multi-operator permissions model. Would require significant capital investment, lack scalability, or reduce strategic control over location, quality and consistency of infrastructure Report P82
  • Rejected: Option 4 sub-choice: Competitive Flexible (multi-stage) Procedure. Not considered necessary given the defined requirement and established market solutions Report P72

Implications

  • Financial: No additional unapproved capital or revenue cost to the Council; most financial, operational and maintenance risk transfers to the operator under a supplier-funded concession-style model. Report 2.3, 2.6, P113
  • Legal: Procurement is a Process 3 procurement under the Council's Contract Procedure Rules, complies with the Procurement Act 2023 and the Public Contracts Regulations 2015, and powers to contract arise from the Local Government (Contracts) Act 1997 and Localism Act 2011. Report 2.4, P116, P117, P118, P119, P120
  • Equalities: The project supports the Council's duties under the Equality Act 2010 by improving access to charging for residents without off-street parking, including those with protected characteristics. Report 5.2, P48
  • Climate: Delivery is expected to cut transport-related carbon emissions and improve air quality by enabling the switch from petrol and diesel vehicles, with positive climate change implications overall. Report 2.1, 2.2, P129, P130, P131
  • Risk: Key risks include limited market interest, electricity network capacity and connection delays, operator performance, transition from existing car park charge points, highways impacts, LEVI funding conditions, and reputational or political sensitivity over charger siting. Report 7.1, P93, P94, P95, P97, P98, P99, P100
  • Staffing: TUPE does not apply: LEVI capability-funded officers remain Council employees and will not transfer to the contractor. Report 9.3

Who and where

  • Medway residents without off-street parking who need access to public EV charging Report 2.2, P28, P29
  • Existing EV charge point users in Medway Council car parks, where performance concerns have been identified Report 6.3, P84
  • Charge point operators bidding for the long-term contract Report P58, P59, P60
  • Local highways, traffic management and electricity network planners Report 3.10, P40, P62
  • OZEV and the Department for Transport as LEVI funders Report 8.4, 8.5

Timeline

  • 16 March 2026: Tender documents issued and Invitation to Tender published Report P75
  • 8 June 2026: Deadline for expressions of interest and shortlisting to 5 suppliers Report P76
  • 15 June 2026: Invitation to Tender issued to the 5 shortlisted suppliers Report P77
  • 20 July 2026: Dialogue with remaining suppliers to commercialise proposals Report P79
  • 27 July 2026: Issuance of final tender documents for final pricing Report P80
  • 7 August 2026: Evaluation of final bids completed, ahead of seeking approval to award Report P81
  • 15 year term, plus 1 year by mutual agreement: Proposed length of the contract with the appointed charge point operator Report P86

Plain English for the jargon

  • LEVI Fund: Local Electric Vehicle Infrastructure Fund, central government funding to support on-street EV charging, particularly for residents without off-street parking.
  • Open Procedure: A single-stage competitive tender under the Public Contracts Regulations 2015 in which all interested bidders submit a tender.
  • Concession-style contract: A contract under which the supplier funds and delivers the service, recovering its costs through charges to users, rather than the Council paying a guaranteed fee.
  • Parent Company Guarantee / Performance Bond: Forms of contractual security that protect the Council if the appointed operator fails to meet its obligations; only one will be required.
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations, governing the transfer of employees on a service provision change; not engaged here.
  • DNO: Distribution Network Operator, the company licensed to distribute electricity in a local area, relevant to grid connection for chargers.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

54/2026 The Cabinet agreed to pursue the procurement for the Supply, Installation, Maintenance and Operation of On-Street Electric Vehicle (EV) charging Infrastructure, as per the preferred option 4 identified in paragraph 6.2.4 of the report. Reasons: Officers recommend approval to commence the procurement of the Supply, Installation, Maintenance and Operation of On-Street Electric Vehicle (EV) Charging Infrastructure in order to support the delivery of Medway Council’s climate change and air quality objectives. The provision of publicly accessible EV charging infrastructure is a key enabler in supporting the transition away from petrol and diesel vehicles, particularly for residents without access to off?street parking. Commencing this procurement will assist the Council in meeting its responsibilities as Highway Authority, contribute to improvements in local air quality, and support the delivery of Medway’s wider climate change commitments. The proposed commercial approach allows the Council to facilitate the delivery of EV charging infrastructure without the need for significant capital investment other than the £2.14m LEVI Grant awarded to us, transferring the majority of financial, operational and maintenance risk the successful operator. A long?term contract term reflects the scale of investment required by the market and is necessary to secure sustainable delivery, ongoing maintenance and service resilience. An Open Procedure is recommended to ensure transparency, fairness and value for money, while encouraging maximum market competition in line with the Public Contracts Regulations 2015. This approach is considered proportionate for the scale, longevity and strategic importance of the project. The proposed approach is to require a single form of contractual security, either a Parent Company Guarantee or a Performance Bond, rather than mandating both. This approach is based on proportionality and informed by market engagement, including review by the Energy Saving Trust, which advised that requiring both a Performance Bond and Parent Company Guarantee in addition to one another could act as a barrier to competition within the specialist on?street EV charging market. The contract adopts a supplier?funded, concession?style model under which the appointed operator will be responsible for capital investment, operation and maintenance of the charging infrastructure. The Council does not provide a guaranteed revenue stream and is not exposed to material direct financial loss. Accordingly, a single, appropriate form of security is considered sufficient to protect the Council’s interests. Approval at Gateway 1 will enable officers to progress this strategically important project in a timely manner, manage identified risks effectively, and establish a scalable model that can support future expansion across other Council?owned land and assets, subject to further approvals.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks approval to commence the procurement process for the Supply, Installation, Maintenance and Operation of On-Street Electric Vehicle Charging Infrastructure.

The project will enable the Council to increase access to public charging for residents without off-street parking, support the transition to electric vehicles improving local air quality and will contribute towards the Council’s climate change and carbon reduction objectives.The Cabinet is asked to agree the procurement timetable and procedure, as set out in paragraph 6.2.4.3.

1. Recommendations 1.1. The Cabinet is asked to agree to pursue the procurement for the Supply, Installation, Maintenance and Operation of On-Street EV charging Infrastructure, as per the preferred option 4 identified in paragraph 6.2.4. 2. Suggested reasons for decisions

2.1Officers recommend approval to commence the procurement of the Supply, Installation, Maintenance and Operation of On-Street Electric Vehicle (EV) Charging Infrastructure in order to support the delivery of Medway Council’s climate change and air quality objectives.

2.2The provision of publicly accessible EV charging infrastructure is a key enabler in supporting the transition away from petrol and diesel vehicles, particularly for residents without access to off-street parking. Commencing this procurement will assist the Council in meeting its responsibilities as Highway Authority, contribute to improvements in local air quality, and support the delivery of Medway’s wider climate change commitments.

2.3The proposed commercial approach allows the Council to facilitate the delivery of EV charging infrastructure without the need for significant capital investment other than the £2.14m LEVI Grant awarded to us, transferring the majority of financial, operational and maintenance risk the successful operator. A long-term contract term reflects the scale of investment required by the market and is necessary to secure sustainable delivery, ongoing maintenance and service resilience.

2.4An Open Procedure is recommended to ensure transparency, fairness and value for money, while encouraging maximum market competition in line with the Public Contracts Regulations 2015. This approach is considered proportionate for the scale, longevity and strategic importance of the project.

2.5The proposed approach is to require a single form of contractual security, either a Parent Company Guarantee or a Performance Bond, rather than mandating both. This approach is based on proportionality and informed by market engagement, including review by the Energy Saving Trust, which advised that requiring both a Performance Bond and Parent Company Guarantee in addition to one another could act as a barrier to competition within the specialist on-street EV charging market.

2.6The contract adopts a supplier-funded, concession-style model under which the appointed operator will be responsible for capital investment, operation and maintenance of the charging infrastructure. The Council does not provide a guaranteed revenue stream and is not exposed to material direct financial loss. Accordingly, a single, appropriate form of security is considered sufficient to protect the Council’s interests.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1 Report: Supply, Installation, Maintenance and Operation of on-Street EV Charging InfrastructureReport 234 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, present
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, present
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present
RH
Richard HicksOfficer, in attendance
KC
Kelly CoggerOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Gateway 1 Report: Supply, Installation, Maintenance and Operation of on-Street EV Charging InfrastructureThis decision
  2. Gateway 3: Supply, Installation, Maintenance and Operation of on-Street EV Charging InfrastructureAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open