Medway Council
Cabinet, Tuesday 30 June 2026 at 7.00pm

Gateway 1 Report: Highways Infrastructure Contract

Agreed Executive 1 paper

AI summaryMedway Cabinet approves start of procurement for a new Highways Infrastructure Contract covering roads and the Medway Tunnel, with contract due to start 1 August 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedThree-lot Highways Infrastructure Contract to be procured
MoneyTotal value in Exempt Appendix 1No figure given in main report
What happens nextTender issued 20 July 2026Contract start targeted for 1 August 2027
Who it affectsHighways, tunnel and capital worksCovers road network and Medway Tunnel

What was decided

The Cabinet agreed to commence procurement of a new Highways Infrastructure Contract in three lots: Lot 1 Highways Term Maintenance, Lot 2 Tunnels Specialist, and Lot 3 Capital Works Framework. Report P28, P29, P30

Lot 1 will be procured using the Competitive Flexible Procedure; Lots 2 and 3 will use the Open Procedure. Report P140, P133, P150

The contract term will be 7 years with an option to extend by 3 years for Lot 1, and 8 years for the Lots 2 and 3 frameworks with reopening points at years 3 and 6. Report P170, P173

Why

The current highways contract is approaching expiry and the Council must meet its statutory duties as Highway Authority under the Highways Act 1980. Report P37, 6.2, P64

An options appraisal scored the Single Supplier Term Maintenance Contract highest, while a framework approach was preferred for tunnel and capital works. Report 2.5, P15, P16

Market engagement through a webinar and questionnaire showed strong supplier interest in the three-lot structure. Report P81, P84, P85, P86, P87

What happens next

Evaluate bids and seek award approval, with a minimum 3-month mobilisation starting by 10 May 2027. Report P161, P162

Award and execute the contract, with service commencement on 1 August 2027. Report P163

The money

  • £5.19M inclusive of VAT FTS works threshold; procurement is above this
  • above £50,000 up to £5m Range of works values for each sub-lot supplier Report P50
  • £25,000.00 Kent Business Portal and Contracts Finder advertising threshold

Options considered

  • Rejected: Do nothing. Would leave no contractual basis for essential highway services and create service, statutory and reputational risks. Report P93, P94, P96
  • Rejected: Extend the current contract. Cannot be extended to provide a compliant long-term solution that meets future requirements. Report P97, P98, P100
  • Rejected: Use an existing framework or external contract. Scope too generic and would reduce Council control over terms, performance and social value. Report P101, P102, P107
  • Rejected: Teckal / vertical arrangement. Highways scope too complex and different from existing arrangement; not deliverable within required timescales. Report P109, P110, P114
  • Rejected: Joint venture or alliance model. Too complex and lengthy to set up for the immediate procurement need. Report P115, P116, P120
  • Rejected: Council-controlled or in-house delivery. Would require significant new capability and longer transition than available. Report P121, P122, P125
  • Chosen: Competitive procurement across three lots. Most appropriate and compliant route, reflecting Medway's specific service requirements and market feedback. Report P126, P127, P131

Implications

  • Legal: Required to discharge statutory duty under the Highways Act 1980; a Find a Tender Service notice will be required; process complies with the Procurement Act 2023 and the Council's Contract Procedure Rules. Report P64, 11.1
  • Financial: Total contract value is an upper ceiling over the full term and is not committed spend; actual expenditure depends on funding approved at the time, including any Department for Transport grants. Report 10.2, 10.3, 10.4
  • Equalities: Social Value commitments covering local employment, apprenticeships, local supply chain spend, healthier communities and carbon reduction will be included in tender and contract KPIs. Report 16.1, 16.2, P219, P220
  • Climate: Contract will generate carbon emissions through materials, plant and construction, but bidders must identify carbon-saving efficiencies and sustainability measures. Report 15.1, 15.2, 15.3
  • Risk: A full procurement risk register has been developed covering programme delivery, affordability, market response, mobilisation and service continuity. Report 8.1, 8.2
  • Staffing: TUPE applies; the detail will be determined by the incumbent supplier during development of the final tender documentation. Report 12.1, P204
  • Other: A Performance Bond or Parent Company Guarantee is requested to be waived for Lot 1 because of KPI clauses, step-in rights and other protections; not required for Lots 2 and 3. Report 5.1

Who and where

  • Road users across Medway, including users of the Medway Tunnel Report P37, 2.8
  • Highways maintenance, tunnel specialist and capital works suppliers in the market Report P80, P83
  • Council staff involved in the existing highways contract where TUPE may apply Report 12.1, P204
  • Medway Council as Highway Authority, discharging duties under the Highways Act 1980 Report P37, P64

Timeline

  • 20th July 2026: Issue tender documents and start of PSQ stage 1 Report P152
  • Friday September 2026 at 5pm: Stage 1 tender submission deadline Report P153
  • Friday October 2026: Evaluation and moderation of Stage 1 submissions Report P154
  • October 2026: Issue invitation to submit Initial Tender documents to 3-5 shortlisted suppliers Report P155
  • Friday March 2027: Evaluation of final bids to identify winning bidder Report P161
  • Latest 10th May 2027: Minimum 3-month supplier mobilisation start date Report P162
  • 1st August 2027: Contract commencement Report P163

Plain English for the jargon

  • HIC: Highways Infrastructure Contract, the new contract being procured.
  • Lot: A separate procurement strand within the overall contract, with its own suppliers and terms.
  • Competitive Flexible Procedure: A multi-stage procurement procedure under the Procurement Act 2023 that allows shortlisting, negotiation and refinement of bids.
  • Open Procedure: A single-stage procurement where all interested suppliers may submit a tender.
  • SPI: Strategic Performance Indicator, used to assess overall contract wellbeing and longer-term outcomes.
  • KPI: Key Performance Indicator, used to measure day-to-day operational delivery.
  • EIC: Efficiency and Innovation Card, a structured bidder proposal for service improvement or savings.
  • FTS: Find a Tender Service, the UK public sector tender publication platform.
  • Teckal: A vertical arrangement between a contracting authority and a controlled company that may be exempt from full competition.
  • LGR: Local Government Reorganisation, restructuring of local authority boundaries or functions.
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations governing staff transfers.
  • DfT: Department for Transport, a potential source of grant funding for highways works.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

103/2026 The Cabinet agreed to the commencement of the procurement of a new Highways Infrastructure Contract (HIC) that would ensure the continued delivery of essential services required to maintain Medway’s highway network and critical infrastructure assets, including the Medway Tunnel, in accordance with the Highways Act 1980.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Summary

This report seeks permission to commence the procurement of the Highways Infrastructure Contracts.

1. Recommendation 1.1 The Cabinet is recommended to agree to commence the procurement of a new Highways Infrastructure Contract (HIC) that will ensure the continued delivery of essential services required to maintain Medway’s highway network and critical infrastructure assets, including the Medway Tunnel, in accordance with the Highways Act 1980. 2. Suggested reasons for decision

2.1The proposed contract model and recommendations have been developed following a comprehensive options appraisal carried out in spring 2026. This process drew on input from Medway officers, a review of the current service, market engagement (including a supplier webinar and questionnaire), and specialist technical and procurement advice from Founds Group.

2.2The recommended approach is supported by the Options Appraisal Report and its supporting documents. These include the Contract and Procurement Strategy, Market Engagement Summary Report, Medway Key Findings Report, and Tunnel Strategy. Together, these provide the evidence and rationale for the proposed approach and are available for review.

2.3The options appraisal followed a two-stage process:

2.3.1 A qualitative assessment of each contract model against Medway’s agreed suitability drivers.

2.3.2 A quantitative assessment of each option against corporate and strategic objectives, service priorities, and operational requirements, using an agreed scoring methodology.

2.4The suitability drivers were informed by the Medway Key Findings Report and reflect the key outcomes required from the future contract, based on current service experience and identified areas for improvement.

Service quality, Integrity and assurance, evidence-based delivery, control active performance management

pricing clarity, spend visibility, Value for money and transparency fair/evidenced payment

reduced duplication/friction, Efficiency and simplification streamlined processes/specification

resilience, succession, workforce People, capability and resourcing development decision-making clarity, appropriate Governance, assurance and incentives/penalties, consistent contract discipline administration Collaboration and stakeholder partnership working, public/political confidence confidence, visible outcomes

2.5The appraisal shows that a Single Supplier Term Maintenance Contract is the most suitable and highest-scoring option for delivering the core services in Lot 1. It also confirms that a framework approach is more appropriate for specialist and capital works, where the Council needs access to a wider and more flexible supply chain.

Contract Qualitative Quantitative Overall Appraisal model score score position outcome

Single Preferred Supplier 25/30 12.50 1st core model TMC

Retained for Framework specialist Delivery 20/30 11.80 2nd and capital Model frameworks

Teckal 19/30 11.49 3rd Not preferred

Not JV / Alliance 18/30 - Not preferred progressed

Council- controlled / Not 14/30 - Not preferred in-house progressed delivery

2.6The recommended approach is therefore a combined model comprising:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 1 Report: Highways Infrastructure ContractReport 527 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, apologies
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, present
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, apologies
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, present
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present
AM
Andy McNally-JohnsonOfficer, in attendance

On this subject at Medway

Search all
  1. Gateway 1 Report: Highways Infrastructure ContractThis decision
  2. Gateway 5 Contract Management Report: Waste Collection and Disposal, Household Waste Recycling Centres, Tree Maintenance and Highways Minor WorksNoted
  3. Gateway 5 Procurement Contract Management Report: Highways Minor Works Contract Performance ReviewNoted
  4. Gateway 5 Procurement Contract Management Report: Highways Minor Works Contract Performance ReviewNoted
  5. Gateway 4 Contract Management: Highways Minor Works ContractNoted
  6. Gateway 4 Contract Review: Highways Minor Works ContractDecided

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open