Melton Borough Council
Cabinet, Wednesday 17 December 2025 at 4.30pm

Stockyard Update

Noted Executive 5 papers

AI summaryMelton Cabinet approves two-stage procurement for Stockyard main construction contract, retains Scalford Road car park, and approves design revisions within the existing capital budget.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeNotedTwo-stage construction procurement, car park retained, Cultural Hub in principle
MoneynullDesign revisions to be accommodated within approved Capital Programme Budget
What happens nextNot stated
Who it affectsNot stated

What was decided

Cabinet approved a two-stage procurement process for the main construction contract, replacing the previous decision to make a direct award through a framework, to maximise value for money using the additional time available.

Cabinet approved the design revisions identified through the RIBA Stage 4 review, noting they can be accommodated within the approved current Capital Programme Budget, and approved in principle the development of a Cultural Hub on the site with Loughborough College.

Cabinet reversed its earlier disposal decision and approved that Site 1b Scalford Road Car Park be retained as a car park within the council's asset portfolio, to accommodate revised car parking arrangements on the Stockyard site.

Why

The Government has confirmed an updated completion deadline of March 2028 for LUF projects, giving additional time that the council wishes to use to secure better value through competition rather than a direct award.

The RIBA Stage 4 review, including a design review and operator review, identified the need for design changes and a new approach to appointing an operator, which Cabinet accepted.

What happens next

The Director for Place and Prosperity, in consultation with the Leader and Monitoring Officer, will run the two-stage procurement and enter into a JCT Design & Build 2024 contract for the main construction works within the approved capital budget.

The reprofiled Capital Programme will be presented to full Council at the budget setting meeting in February 2026.

Any necessary Section 73 planning applications or reserved matters will be submitted to secure the approved design changes, and the council will work with Loughborough College and other partners to submit funding bids for the Cultural Hub. Cabinet also asked to see detailed layouts of the public toilet facilities on site.

Options considered

  • Rejected: Direct award through a framework (previous decision). Additional time available under the new March 2028 LUF deadline allows the council to seek better value for money through competition
  • Chosen: Two-stage procurement process for the main construction contract. Maximises value for money using the additional time available under the revised LUF completion deadline
  • Rejected: Dispose of Site 1b Scalford Road Car Park (previous decision). Site is now needed to accommodate revised car parking arrangements on the Stockyard site
  • Chosen: Retain Site 1b Scalford Road Car Park within the council's asset portfolio. Needed to accommodate design changes relating to car parking on the Stockyard site

Implications

  • Financial: The reprofiled Capital Programme will go to full Council in February 2026; design revisions are to be met from the existing approved Capital Programme Budget.
  • Legal: A JCT Design & Build 2024 contract will be used for the main construction works; Section 73 or reserved matters planning applications will be submitted for the design changes.
  • Other: The council will work with Loughborough College and other partners to develop a Cultural Hub on the site and submit funding bids to secure further investment.
  • Other: Cabinet specifically asked to see detailed layouts of the public toilet facilities on site.

Who and where

  • Future main construction contractor (to be appointed through two-stage procurement)
  • Loughborough College (named partner for Cultural Hub development and funding bids)
  • Users of Site 1b Scalford Road Car Park, which will be retained rather than disposed of
  • The future operator of the Stockyard, to be appointed following the Operator Review

Timeline

  • February 2026: Reprofiled Capital Programme to be considered by full Council at the budget setting meeting
  • March 2028: Updated Government completion deadline for Levelling Up Fund projects

Plain English for the jargon

  • RIBA stages: Royal Institute of British Architects work stages, from 0 (strategic definition) to 7 (in use); Stage 4 is technical design and Stage 5 is construction.
  • LUF: Levelling Up Fund, the Government programme from which the Stockyard project is funded.
  • JCT Design & Build 2024: Standard form of construction contract published by the Joint Contracts Tribunal, under which the contractor takes responsibility for both design and construction.
  • Section 73 application: An application under Section 73 of the Town and Country Planning Act to vary or remove conditions attached to an existing planning permission.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item62

Resolved

That Cabinet: 1. NOTED the progress update on the Stockyard project, including the completion of the RIBA stage 4 programme review, including a design review and operator review and considers the following recommendations arising: Project Team: 2. NOTED the updates in governance and project structure at appendix 1a and appendix 1b and, approves the appointment of the delivery team to support the Council in delivering RIBA stages 5 -7. 3. DELEGATED AUTHORITY to the Director for Place and Prosperity in consultation with the Portfolio Holder for Corporate Finance, Property and Resources and the Monitoring Officer to enter all necessary legal agreements and contracts. Construction Procurement: 4. NOTED the Government has confirmed that LUF projects have an updated completion deadline of March 2028, and the updated programme timeline and delivery schedule. 5. NOTED that the reprofiled Capital Programme will be considered by Council at the budget setting meeting in February 2026. 6. On the basis of the additional time available and to maximise value for money, amend the previous decision for a direct award through a framework and instead APPROVED the initiation of a two-stage procurement process for the main construction contract. 7. APPROVED the Procurement Strategy and principles which will govern the procurement process and set out in section 5.2 and 5.3. 8. Following the procurement process, DELEGATED AUTHORITY to the Director for Place and Prosperity, in consultation with the Leader of the Council and the Monitoring Officer to utilise a JCT Design & Build 2024 contract and enter into the necessary contracts and legal agreements keeping within the approved capital budget. Design Revisions: 9. APPROVED the suite of design revisions identified through the RIBA Stage 4 review, and set out in section 5.4, noting these can be accommodated within the approved current Capital Programme Budget. 10. NOTED progress made towards incorporating the LUF specified cultural outputs within the Stockyard and approve in principle the development of a Cultural Hub on the site and, working with Loughborough College and any other stakeholders and partners, approve the submission of any funding bids to relevant parties to secure further investment. 11. APPROVED the submission of any relevant Section 73 (variations) or reserved matters planning applications required to secure approved design changes. 12. DELEGATED AUTHORITY to the Director for Place and Prosperity in consultation with the Portfolio Holder for Corporate Finance, Property and Resources to accommodate the design revisions within the overall budget profile and submit and manage all necessary planning applications and consents. Cabinet stated that they would like to see detailed layouts of the public toilet facilities on site. 13. To accommodate design changes relating to car parking on the site, amend the previous decision to dispose of site 1b Scalford Road Car Park and instead APPROVED that it now be retained, as a car park, within the asset portfolio of the Council. Operator Strategy: 14. NOTED the outcomes of the Operator Review and based on the comprehensive financial appraisal, approve the Operator Strategy to include the following: 14.1. The Council would ...
Word for word from the decision Melton published for this meeting. Source: democracy.melton.gov.uk

Follow this further

Built from Melton's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Stockyard Programme Board StructureAppendix 1a 58 KB Copy on its way
PDF
Stockyard Operational StructureAppendix 1b 98 KB Copy on its way
PDF
Anchor Building Ground floor planAppendix 3a 253 KB Copy on its way
PDF
Anchor Building: First floor planAppendix 3b 250 KB Copy on its way
PDF
Stockyard UpdateReport 2 MB Copy on its way

At this meeting

Whole meeting
62Stockyard UpdateThis decision

On this subject at Melton

Search all
  1. Stockyard UpdateThis decision
  2. Disposal linked with the cattle market/stockyard site (site 1b)Decided
  3. Contract award for the construction phase of the stockyard redevelopment projectAgreed
  4. Levelling up fund update - stockyard planning applicationNoted

More from Melton Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Matters referred from Scrutiny Committee in accordance with Scrutiny Procedure RulesHousing Revenue Account Business Plan and Asset Management Plan Cabinet AGREED to have regard for the Scrutiny Commit... Agreed Open
8 Sep 2026 Housing Revenue Account Revenue and Capital Budget Monitoring Report 2026/27, Quarter 1Cabinet NOTED the financial position on the HRA at 30 June 2026 and the year-end forecast for both revenue and capital. Noted Open
8 Sep 2026 General Fund and Special Expenses - Revenue and Capital Budget Monitoring 1 April 2026 to 30 June 2026That Cabinet NOTED the year end forecast and financial position for the General Fund and Special Expenses at 30 June ... Noted Open
8 Sep 2026 Treasury Management Report Quarter 1 2026/27That Cabinet: 1) NOTED the Quarter 1 position on treasury activity for 2026/27. 2) NOTED the Quarter 1 position on Pr... Noted Open
8 Sep 2026 Annual Complaints Report 2025/26That Cabinet: 1) APPROVED the Council’s refreshed Customer Feedback and Complaints Policy shown in Appendix 1. 2) APP... Approved Open