Melton Borough Council
Cabinet, Tuesday 8 September 2026 at 5.30pm

Asset Development Programme Update - Parkside and Phoenix House

Approved Executive 1 paper

AI summaryCabinet approved a revised Parkside delivery plan that adds a Community Hub, reconfigures accommodation, and drops the commercial office element. Focus Consultants will continue as project managers.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedIncludes Community Hub and reconfiguration
MoneyNot stated
What happens nextDirector for Place and ProsperityTo lead design, procurement and delivery
Who it affectsParkside building and servicesCustomer-facing and community services

What was decided

Cabinet approved the revised Parkside delivery option so the scheme stays financially viable and within the approved budget and programme.

Cabinet approved creation of a Community Hub at Parkside to provide an accessible location for customer-facing and community services and to support service integration.

Cabinet approved reconfiguration of Parkside accommodation to allow more intensive and efficient use of the building and improve operational flexibility.

Why

The revised option is needed to keep the scheme financially viable and deliverable within the approved budget and programme.

The Community Hub is intended to support improved service integration between customer-facing and community services.

Reconfiguration is intended to deliver more intensive and efficient use of the building and greater operational flexibility.

What happens next

Focus Consultants will continue providing project management services through delivery and completion of the project.

The Director for Place and Prosperity, in consultation with the relevant Portfolio Holder, will approve detailed design, procurement arrangements, contract award and project implementation within the approved budget.

The previously approved commercial office accommodation element will not be taken forward, though the core strategic objectives of the Asset Development Programme are retained.

Implications

  • Financial: The scheme must remain financially viable and be delivered within the approved budget.
  • Other: The previously approved commercial office accommodation at Parkside is excluded from the revised scheme.
  • Other: Parkside is to be used more intensively, with reconfigurable space supporting greater operational flexibility.

Who and where

  • Users of customer-facing and community services at Parkside
  • Council staff and operations based at Parkside
  • Suppliers and contractors engaged through the procurement approach set out in the report

Plain English for the jargon

  • Asset Development Programme: The council's programme covering work on its own buildings, including Parkside and Phoenix House.
  • Community Hub: An accessible location bringing together customer-facing and community services to support service integration.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That Cabinet: 1) APPROVED the revised Parkside delivery option, as set out in this report, to ensure the scheme remains financially viable and can be delivered within the approved budget and programme. 2) APPROVED the creation of a Community Hub at Parkside, providing an accessible location for customer-facing and community services and supporting improved service integration. 3) APPROVED the reconfiguration of accommodation within Parkside to facilitate more intensive and efficient utilisation of the building and improve operational flexibility. 4) NOTED that the revised scheme excludes the previously approved commercial office accommodation element but retains the core strategic objectives of the Asset Development Programme. 5) APPROVED the procurement approach and delivery strategy set out within this report for implementation of the revised Parkside scheme. 6) APPROVED the appointment of Focus Consultants to continue providing project management services through delivery and completion of the project. 7) DELEGATED AUTHORITY to the Director for Place and Prosperity, in consultation with the relevant Portfolio Holder, to undertake all actions necessary to deliver and complete the project, including approval of the detailed design, procurement arrangements, contract award and project implementation, within the approved budget.
Word for word from the decision Melton published for this meeting. Source: democracy.melton.gov.uk

Follow this further

Built from Melton's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Asset Development Programme Update: Parkside and Phoenix HouseReport 201 KB Copy on its way

At this meeting

Whole meeting

On this subject at Melton

Search all
  1. Asset Development Programme Update - Parkside and Phoenix HouseThis decision
  2. Asset Development Programme UpdateNoted
  3. Asset development programme update - proposal for diversification of the parkside offices by way of a proposed new hotel developmentNoted
  4. Business rates pool funding update - asset development programme phase 1Noted

More from Melton Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Matters referred from Scrutiny Committee in accordance with Scrutiny Procedure RulesHousing Revenue Account Business Plan and Asset Management Plan Cabinet AGREED to have regard for the Scrutiny Commit... Agreed Open
8 Sep 2026 Housing Revenue Account Revenue and Capital Budget Monitoring Report 2026/27, Quarter 1Cabinet NOTED the financial position on the HRA at 30 June 2026 and the year-end forecast for both revenue and capital. Noted Open
8 Sep 2026 General Fund and Special Expenses - Revenue and Capital Budget Monitoring 1 April 2026 to 30 June 2026That Cabinet NOTED the year end forecast and financial position for the General Fund and Special Expenses at 30 June ... Noted Open
8 Sep 2026 Treasury Management Report Quarter 1 2026/27That Cabinet: 1) NOTED the Quarter 1 position on treasury activity for 2026/27. 2) NOTED the Quarter 1 position on Pr... Noted Open
8 Sep 2026 Annual Complaints Report 2025/26That Cabinet: 1) APPROVED the Council’s refreshed Customer Feedback and Complaints Policy shown in Appendix 1. 2) APP... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies