Merthyr Tydfil County Borough Council
Cabinet, Wednesday 29 June 2005 at 2.30pm

Proposed Regeneration Programme at Pant Industrial Estate

Decided Executive 1 paper

Cabinet decided this item on Wednesday 29 June 2005. Below is the council's own wording, with the papers it was decided on.

Item856

Resolved

Councillor A Jones led Cabinet through the report. RECOMMENDATION That cabinet accepts tender 4 – Austin Smith Lord £24,325.10 for the reasons outlined in this report. RESOLVED To accept the recommendation set out above.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet

Purpose of report

To inform members of the submissions regarding the above tender and proposed timetable for the initial phase of development work at Pant Industrial Estate

Background

1.1At the Cabinet meeting, held on 4th May 2005, Members approved in principle an initial phase of development work for the Pant Industrial Estate funded through the Councils successful Welsh Assembly Government Physical Regeneration Fund approval.

1.2As part of this process, a brief was prepared by the Regeneration Department to invite submissions for the preparation of a Conceptual Framework Strategy for the Pant Industrial Estate, as a first stage in a wider programme of development work. The main focus of the study will be:

• Improving the environmental quality of the Estate in respect of image, infrastructure, way-finding, orientation, landscape and boundary treatments.

• Raising awareness and the development of a sustainable agenda for the future of the Estate.

2.0APPOINTMENT OF CONSULTANTS

2.1A budget of £25,000 was identified in the PRF application and budget guidance was included in the tender brief. Although a formal tendering process was not necessary, formal quotations were received from five consultants.

2.2Submissions were returned for the above study on Friday 6th May and were as follows:

1. Groundwork: £19,000.00 2. White Green Young: £22,500.00 3. TACP: £22,530.12 4. Austin Smith Lord: £24,325.00 5. Landscape Design Associates: Did not submit

2.3All four consultancies were invited to interview on Friday 13th May and asked to make a 20 minute presentation expanding on their bid with questions from the interview panel that comprised of a sub group of officers from the client team.

2.4A semi-quantitative score card was used for selecting the consultants based upon experience, the project team, response to the brief and price. The tender panel discussed individual markings to arrive at a consensus assessment.

2.5It was considered that Austin Smith Lord should be awarded the commission in the tender amount of £24,325.00 based primarily on their clear understanding of the brief and the associated design principles and work programme.

2.6Austin Smith Lord were appointed on May 16th 2005 to undertake a Conceptual Framework Strategy over a ten week work programme. All works required within the brief are to be completed by end July 2005, allowing scope to submit a further PRF bid(s) to take forward the study findings. Further reports will be issued in due course to keep Members informed.

Financial implications

3.1This development study does not require any financial contribution from the Council; however Officer time will be required, particularly from the Council’s Business Environment Co-ordinator who will be primarily responsible for assisting the consultants in providing baseline data and information in support of this work.

Recommendation

4.1It is RECOMMENDED that Cabinet accepts tender 4 – Austin Smith Lord £24,325.10 for the reasons outlined in this report.

JILL SHUKER DIRECTOR, CORPORATE CENTRE

INTERNAL REPORT CONSULTATION:

The following officers have been consulted in respect of the proposals and recommendations set out in this report.

Chief Executive Director of Director of Director of Director of Chief Officer, Integrated Adults, Families Customer Customer Finance, Audit Children’s and Lifelong Community Corporate and Risk Services Learning Services Services Management BACKGROUND PAPERS:

Title of Document(s) Document(s) Date Document Location

• A Sustainable Business Park Various Regeneration Department Development Study at Pant Industrial Estate Consultants Brief, April 2005. • Pant Industrial Estate PRF application, January 2005. • Consultants Tender Submissions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Regeneration Programme at Pant Industrial EstateReport 69 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. Proposed Regeneration Programme at Pant Industrial EstateThis decision
  2. Penderyn Square and River Taff Central Link Regeneration Projects - Proposed Permanent Traffic Regulation OrdersDecided
  3. Trelewis Regeneration Scheme - Petition and Proposed Permanent Traffic Regulation OrderDecided
  4. Penderyn Square Regeneration Project - Proposed Permanent Traffic Regulation OrdersDecided
  5. Proposed Taff Bargoed Regeneration StrategyDecided

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies