Resolved
Councillor B Toomey led Cabinet through the report. RECOMMENDATIONS In view of the benefits to the Council in making good the retaining wall alongside No.2, The Gardens, Quakers Yard, it is recommended that the most economical option of carrying out the required works is followed and the resulting total cost shared with the property owners, on a without prejudice basis, in the ratio of 51/49% in the Council’s favour. If after following conventional tendering procedures it proves more economically advantageous to carry out the repair works as a “joint venture”, as described in 8.0 above, then this course of action is followed. RESOLVED To accept the recommendations set out above.