Cabinet, Wednesday 7 September 2005 at 2.30pm

Local Regeneration Fund - Match Funding Pot

Approved Executive 1 paper

Cabinet approved this item on Wednesday 7 September 2005. Below is the council's own wording, with the papers it was decided on.

Item120

Resolved

Councillor A Jones led Cabinet through the report. RECOMMENDATION That Councillors approve the recommendation for the allocation of the Local Regeneration Match Funding pot as set out above. RESOLVED To accept the recommendation stated above.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 4 pages

Purpose of report

To seek formal approval for an application to the Local Regeneration Match (LRF) Funding Pot

1.0INTRODUCTION

1.1Previous reports to Cabinet have provided information on projects seeking approval for LRF match funding. This report provides details of an additional project, which is now seeking final approval for progression to implementation and allocation of LRF match funding.

2.0PROJECT APPLICATIONS

2.1A summary of the indicative allocations for the next three years is attached at Appendix 1, together with details of previously approved projects. Councillors will note that some of the allocations have been re-profiled over the three financial years identified. This is due to projects being refused by or awaiting approval from the Welsh European Funding Office (WEFO). The additional project requiring commitment is detailed below:

• Priority 6 Measure 1 – Penydarren Tramroad (Completion of Trevithick Trail)

This project has been submitted by the Local Authority under Priority 6, Measure 1 to complete the Trevithick walking and cycle trail from Merthyr Tydfil to Abercynnon. The total project cost is £488,048 towards which a total LRF contribution of £307,000 is being requested. The project has previously been considered and supported as a full application by the Objective 1 Local Partnership and was submitted to a bidding round. It is proposed that it is recommended for approval in order for the project to proceed and the partially constructed trail to be completed.

28 3.0 ROLE OF LOCAL AUTHORITY

3.1Similarly to the first phase of the overall Trevithick Trail project, the Local Authority will manage the project throughout its delivery.

Financial implications

4.1There are no direct financial implications for the Local Authority associated with this report other than staff time associated with managing the scheme, which has been accounted for within the development phase of the project.

Recommendation

5.1That Councillors approve the recommendation for the allocation of the Local Regeneration Match Funding pot as set out above.

JILL SHUKER DIRECTOR OF CORPORATE CENTRE

INTERNAL REPORT CONSULTATION:

The following officers have been consulted in respect of the proposals and recommendations set out in this report.

Chief Executive Director of Director of Director of Director of Chief Officer, Customer Integrated Adults, Families Customer Finance, Audit Corporate Children’s and Lifelong Community and Risk Services Services Learning Services Management

Background papers

Title of Document(s) Document(s) Date Document Location

Local Regeneration Fund Files Various Regeneration Department

29 Appendix 1- Local Regeneration Fund August 2005

Project P- Project Name M Status 2004- 2005- 2006- 2007-2008 2005 2006 2007 Full approval 3-3 Gurnos and Galon 434,680 cap 139,031 cap 24,250 cap Uchaf Community & Physical Regen (obj 1 ref rev rev rev 54147)(3.3R) 5-6 Trevithick 2004 92,000 cap 117,113 celebrations (obj 1 ref 55757)(5.6R) 5-8 Parc Taf Bargoed- 216,583 cap cap cap Pobl a Llefud (obj 1 ref rev rev rev 54634)(5.8A) 5-8 Loops and Links 79,702 cap 22,500 cap cap (obj 1 ref rev rev rev 54729)(5.8A) 5-4 Rural key fund 0 125,215 164,737 90,744 3-4 MTIB Blueprint for 191,568 308,432 the Future 6-3 Merthyr Tydfil Town 0 100,000 100,000 100,000 centre Improvements 1. Sustainable 0 50,280 111,120 48,600 5 Business Parks 3 Greencare Network 0 113,050 134,050 .3

2004- 2005- 2006- 2007-2008 2005 2006 2007 In principle 1-5 Merthyr Tydfil 0 250,000 250,000 approval Business Centre 4-4 vitcc lifelong 0 250,000 250,000 learning centre

2004- 2005- 2006- 2007-2008 2005 2006 2007 Projects 6-1 Penydarren cap 59,700 244,000 0 Under Tramroad Development rev 2000 1300

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Regeneration Fund: Match Funding PotReport 4 pages DownloadRead as text

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies