Councillor W R Roger led Cabinet through the report. RESOLVED To approve the adoption of the bridge abutments and wing walls and authorise the Head of Estates to begin the transfer process. To approve day-to-day maintenance of the structures subject to any significant works requiring Cabinet and Council approval.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
1.1In 1971 the British Rail Board (BRB) conveyed a section of former rail land to Vaynor Quarries. It retained the bridge abutments and wing walls and reserved the right to remove these if they became uneconomical to maintain. In a conveyance dated 16th May 1973 the same land was then transferred to the Breconshire County Council and via local government re-organisation is now in our ownership. The original bridge was removed in 1979 and in 1990 Groundwork Trust used the remaining abutments to construct a footbridge, crossing the road below and improve access to the Taff Trail in that area. This was done without the express permission of the BRB. While the bridge does not directly rest on the structures it does sit on the ground which the BRB would need to remove in dealing with the abutments.
1.2The BRB has given the Authority the option of removing the bridge if we do not wish to take over responsibility. However if the bridge was to be removed there would be a short-term financial implication in the form of demolition costs and a long-term access implication as the bridge links 2 high level sections of the Taff Trail.
1.3The Head of Engineering has been consulted regarding the stability of the structures and no adverse comments have been made.
Financial implications
2.1Each party will be responsible for their own legal costs in the matter.
2.2The Authority will be responsible for the future maintenance of the structures and the Head of Engineering has confirmed that this will come from his Bridges and Structures budget. RECOMMENDATION To approve the adoption of the bridge abutments and wing walls and authorise the Head of Estates to begin the transfer process.
To approve day-to-day maintenance of the structures subject to any significant works requiring further Cabinet and Council approval.
GARETH CHAPMAN DEPUTY CHIEF EXECUTIVE AND DIRECTOR OF CUSTOMER CORPORATE SERVICES
INTERNAL REPORT CONSULTATION:
The following officers have been consulted in respect of the proposals and recommendations set out in this report.
Chief Executive Director of Director of Director of Director Chief Officer, Integrated Adults, Families Customer Corporate Finance, Audit Children’s and Lifelong Community Centre and Risk Services Learning Services Management
Background papers
Title of Document(s) Document(s) Date Document Location
File Ref. Pont.138 Ongoing Estates Division, Ty Keir Hardie
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.