Councillor W A Rogers led Cabinet through the report. RESOLVED That the late objection received be accepted but identified as a late submission. That the Order and objections be forwarded to the Welsh Assembly Government Planning Inspectorate for their consideration as appropriate.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
1.1Councillors will recall that the National Assembly for Wales granted planning permission for the Ffos-Y-Fran Land Reclamation Scheme to Miller Argent (South Wales) Ltd., under Part III of the Town and Country Planning Act 1990 (“The Act”) in the spring of this year. Miller Argent has, as part of the application process, requested the Council to make an Order pursuant to Section 257 of the Act to stop up the various footpaths that lie on the land subject to the planning consent. The application provides for a series of diversions to be provided for the duration of the works along with a purpose built alternative route to preserve access to the Gelligaer Common via an alignment situated clear of the working void and storage area.
1.2The Director of Customer Corporate Services was duly authorised to execute the appropriate processes to make the necessary Order(s) (Item No.626, Cabinet 23.02.05. refers).
1.3In June of this year following objections received after statutory consultation, Councillors resolved to withdraw the Order(s) on the basis that the content of various objections related to a complex area of law and were of the view that the public interest would be best served by the withdrawal of the Order(s). Councillors also resolved to approve the preparation of a new revised Order (Minute No. 863 refers).
2.0Present Position
2.1The revised Order was published on September 22nd 2005 and advertised in accordance with statutory requirements. The objection period for this process has now ended and a total of twenty two objections were received before the due date. One objection was received three days after the due date. 2.2 The majority of the letters received relate to objectors’ belief that the footpath closure order was being published prematurely in the light of a legal challenge to the decision on planning consent for the Ffos-Y-Fran project. A High Court hearing of the challenge is due to take place in December 2005. The timing of the judicial review is not of itself a ground for objection to the Order and I have written to the objectors advising them accordingly but to date, none of the objections has been withdrawn. A number of objections also relate to the fact that claimed rights of way are not included in the Order. In law the claimed rights of way have no legal status, and hence are not included in the Order. These objections are therefore not relevant to the substantive issue but will, for completion, be brought to the attention of the Welsh Assembly Government Planning Inspectorate. Additionally objectors were concerned that the Stopping Up Order would be effective from October 2005 thus depriving the public of half a year of access to the area prior to the reclamation works being carried out. This is also a misapprehension.
2.3The Authority has taken steps to respond to objectors explaining the facts, and asking them to withdraw their objections. No objections have been withdrawn to date and the responses suggest that a consensual withdrawal is unlikely.
2.4As the objections have not been withdrawn, the next appropriate stage is to forward the objections with all subsequent correspondence to the Welsh Assembly Government Planning Inspectorate for their consideration and ultimate determination of the application by the Welsh Assembly Government.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.