Planning, Regulatory and Licensing approved this item on Wednesday 21 December 2005. Below is the council's own wording, with the papers it was decided on.
RESOLVED That the Planning & Regulatory Committee approves the Merthyr Tydfil Delivery Agreement including all resource implications arising. That the document be submitted to the National Assembly for Wales for agreement. That following National Assembly agreement, the document be published on the Council’s website and made available for inspection in the Councillor’s Library and at Ty Keir Hardie. That the financial implications of the LDP process over the next three financial years, as set out an Para 4.1 above, of the Delivery Agreement be taken into account when setting the Revenue Budget for the Planning Division for the financial years 2006/07, 2007/08 and 2008/09. That this report be referred to Council for adoption.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
Report to Planning, Regulatory and Licensing, 48 pages
MERTHYR TYDFIL COUNTY BOROUGH COUNCIL
DATE WRITTEN 21st November 2005 REPORT AUTHOR Chris Edwards COMMITTEE Planning & Regulatory COMMITTEE DATE 21st December 2005
Chairman, Ladies and Gentlemen,
Merthyr Tydfil Local Development Plan - Delivery Agreement
Purpose of this report
To advise Councillors of progress on the Merthyr Tydfil Local Development Plan (LDP) and to seek approval of the LDP Delivery Agreement (hereinafter referred to as the Delivery Agreement) prior to its formal submission to the National Assembly for agreement.
1.0Introduction
1.1Councillors will be aware that the Planning Division has been engaged on preparatory work for the new Merthyr Tydfil Local Development Plan. The new plan will set out the Council’s priorities for the sustainable development and use of land within the County Borough between 2006 and 2021 having regard to the Council’s Vision and a wide range of other plans and strategies.
1.2Once adopted, the LDP will supersede the existing Merthyr Tydfil Borough Local Plan (adopted May 1999) and the existing Mid Glamorgan (Merthyr Tydfil County Borough) Replacement Structure Plan (adopted August 1996) as the primary tool for guiding development and steering decisions taken on planning applications.
1.3The LDP will also provide an opportunity to utilise much of the work that had already been undertaken on the Merthyr Tydfil Unitary Development Plan prior to the Welsh Assembly Government advising that preparation of that plan should cease.
2.0The LDP Delivery Agreement
2.1Local Development Plans were introduced by the Planning & Compulsory Purchase Act 2004, which requires the Council to commence plan preparation by agreeing a Delivery Agreement with the National Assembly. This must include:
• a Community Involvement Scheme (CIS) – indicating how the Council will involve consultation bodies and the public in the plan preparation process; and • a Timetable for preparing and adopting the LDP, and for preparing and publishing the sustainability report and the Annual Monitoring Report. 2.2The Delivery Agreement is an important part of the plan preparation process and delivery of the plan in accordance with the Delivery Agreement will be one of the tests of the plan’s ‘soundness’ when examined by an independent Planning Inspector.
2.3The full text of the Delivery Agreement for Councillors’ information is appended to this report DOC 1 refers.
3.0Consultation on the Delivery Agreement
3.1The Town & Country Planning (Local Development Plans) (Wales) Regulations 2005 require that, before formally approving and submitting a Delivery Agreement to the Assembly, the Council must consult those bodies it considers to potentially have an interest in development matters. This consultation applies to both the timetable for plan preparation and the community involvement scheme.
3.2Consultation on the Delivery Agreement took place between 19th October and 11th November 2005. Of the 55 targeted bodies that were consulted, four replied representing a response rate of around 7%.
3.3The responses received have been analysed and have been found to be largely supportive of the Council’s approach to putting a new LDP in place during the specified timescale of just over three and a half years. However, a number of changes were requested which would help clarify the consultation process and provide a clearer mechanism for reporting back the results of each stage of consultation.
3.4My Head of Planning’s analysis and response to the comments received are included as Appendix 6 of the Delivery Agreement and, where appropriate, the contents of the Agreement have been modified in the light of those comments.
4.0Financial implications of the LDP process
4.1The Delivery Agreement clearly sets out the implications arising from the future LDP process at Figure 4 (Page 15). It is considered that the total cost of plan preparation will be £119,000 which is broken down as follows:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Regulatory and Licensing at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.