Councillor A Jones led Cabinet through the report. It was stated that a change be made to paragraph 2 of the recommendations and that work undertaken by the Estates department to carry out a review of the Castle be used as match funding and that paragraph 2 be amended to this effect. After discussion it was RESOLVED That Councillors approve the submission of the Project Planning Grant application for the maximum of £50,000.00 to the Heritage Lottery Fund in order to take forward recommendations set out in the Cyfarthfa Masterplan. That work undertaken by the review undertaken by Estates department of the Cyfarthfa Castle be used as match funding.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
To inform Councillors and seek formal approval of the development and submission of a project planning grant to the Heritage Lottery Fund in respect of Cyfarthfa Park and Castle.
1.0INTRODUCTION
1.1In December 2004 White consultants completed the final version of the Cyfarthfa Heritage Area Masterplan, this identified a series of projects and several potential funding sources to deliver specific phases within the plan. The Heritage Lottery Fund (HLF) was highlighted as the key funding body, focusing on two specific programmes: Parks for People and Heritage Lottery Grants. (A summary of these grant programmes are provided at Appendix 1 and further information has been made available in the Members’ Library).
1.2In October 2005 an internal steering group was established to identify potentially eligible projects from the masterplan and to agree a way forward on their implementation. A consultation event was held with relevant stakeholders on 18th January 2006, with further consultation events planned as the project progresses. It is anticipated that a more formal Cyfarthfa Park Stakeholder group will be established when required.
2.0CURRENT SITUATION
2.1Following advice from the Heritage Lottery Fund and CADW it has been agreed that Cyfarthfa Park and Cyfarthfa Castle cannot be looked upon as separate projects and that they should be viewed as separate elements of one large project that is progressed via an integrated approach. The Heritage Lottery Fund has, however, indicated that it will not support two large–scale applications at one time. Consequently, a decision will need to be taken whether the Castle or Park is developed as a first stage in the overall project. This will need to be informed by comprehensive assessments that will form part of the pre-project planning grant stage. 2.2 The Heritage Lottery Fund currently offer Project Planning grants (PPG’s) of up to £50,000 to help organisations applying to either Parks for People or Heritage Grants. These grants support specific feasibility and assessment work that will contribute to the project planning process and identify / provide justification for the ‘timing’ of various project stages. Examples of work funded through PPGs include:
- an access plan involving research to inform improved access to heritage; - a conservation management plan to create a better understanding of the heritage site, collection or object, and plans for how it will be managed to conserve its significance; - an audience development plan involving research to support the development of new audiences for the heritage offer; and - other necessary specialist conservation reports, such as structural surveys or conservator’s reports.
3.0PROPOSAL
3.1It has been recommended by the Heritage Lottery Fund that the Local Authority apply for a PPG to carry out such specific research on both the Park and Castle. When completed, this work should provide a justified prioritisation of which element of the overall project (i.e. the Castle or Park) and associated funding applications (i.e. a ‘Parks For People’ focusing on the surrounding park or a ‘Heritage Grant’ focusing on the Castle) should be progressed.
4.0IMPLICATIONS FOR OTHER HERITAGE BASED APPLICATIONS
4.1If an application is submitted to Parks For People or the Heritage Grants programme there will be a potential delay on other large-scale applications to HLF for the Borough until at least 2009 (this excludes any Townscape Heritage Initiative projects). Alternative sources of funding may however be available for such developments, (for example the post 2006 European Structural Fund Programme).
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.