Resolved
[name removed] led Cabinet through the report. RESOLVED That Cabinet approve the Corporate Procurement Plan 2006 – 2010 and recommends its acceptance to Council. An Action Plan will be drawn up as outlined in Paragraph 3 of the report.
Cabinet approved this item on Wednesday 22 March 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
[name removed] led Cabinet through the report. RESOLVED That Cabinet approve the Corporate Procurement Plan 2006 – 2010 and recommends its acceptance to Council. An Action Plan will be drawn up as outlined in Paragraph 3 of the report.
To report to Cabinet on the Corporate Procurement Plan for 2006 - 2010
1.0INTRODUCTION
1.1Merthyr Tydfil County Borough Council’s Corporate Procurement Plan for 2006 - 2010 sets out to develop a first class procurement function for the Council, through primarily seeking to develop procurement competence, improve procurement processes & procedures and maximise efficiency gains in order to deliver Value for Money and organisational improvements that directly support the overall aims & objectives of the Council.
1.2The Procurement Plan presented to Cabinet links to the Public Sector Procurement Efficiencies promoted by Central Government which became embodied in the 2004 Spending Review of Sir Peter Gershon (The Gershon Report) and the Welsh Assembly Governments publication document ‘Making The Connections’.
1.3The Procurement Plan is designed as a flexible plan that will continuously evolve and grow up-to 2010. In 2010 a fundamental review of the plan will take place in order to establish the Council’s future procurement requirements, developments and strategies.
1.4In support of this we aim to establish clear corporate foundations for the procurement activity that will enable us to build upon previous purchasing efficiencies that the Council’s devolved powers have realised.
1.5To establish these corporate foundations for the procurement function it will be essential to develop and maintain professional dedicated procurement resource corporately, that can take on the responsibility for implementing and adopting a series of continuously evolving policies that will introduce flexibility to current practices so that the Council can continuously establish better procurement practices that keep pace with modern public procurement developments. 2.0 THE CORPORATE PROCUREMENT PLAN
2.1The Corporate Procurement Plan set out in the document at Appendix 1 details 4 distinct categories which make up the whole Procurement Plan. These are:-
1. The Corporate Procurement Strategy, giving clear direction for all of the Council’s stakeholders
2. A Strategic Action Plan, focusing on the development of strategic procurement
3. Modernised Procurement Processes & Procedures (Rules), replacing existing procurement & contracting regulations/ contracting standing orders
4. Procurement Manual and Guidance, supporting the newly evolving procurement processes & procedures
2.2The timetable for delivering these Procurement objectives is set out in the Key Strategic Priorities (KSP’s) which are maintained on the Council’s ‘Q’ Drive.
3.0ACTION PLAN
3.1If Cabinet are minded to approve this Procurement Plan a detailed Action Plan will need to be developed which will identify those changes that will be required to those service areas that will be affected.
4.1Clearly there will be financial implications from the acceptance of this report. However these are not at this time quantifiable and will require further reporting to Cabinet and Council where appropriate. Financial Efficiency benefits to the Authority will also result from this plan.
4.2There may also be the need for additional resources to enable efficiencies to be achieved and again these will be reported further to Cabinet/Council when known.
5.1I recommend that Cabinet approves the Corporate Procurement Plan 2006 - 2010 and recommends its acceptance to Council.
5.2Following recommendation of acceptance by Cabinet an Action Plan will be drawn up as outlined in paragraph 3.
HUGH O’SULLIVAN CHIEF OFFICER, FINANCE, AUDIT AND RISK MANAGEMENT INTERNAL REPORT CONSULTATION:
The following officers have been consulted in respect of the proposals and recommendations set out in this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Procurement Plan 2006-2010Report | 3 pages | DownloadRead as text |
PDF |
Item 10aReport | 40 pages | Download |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.