Councillor W R Smith left the meeting. Councillor A Jones led Cabinet through the report. Questions were raised regarding the amount of Officer time required. It was confirmed that only a small amount of Officer time would be required and that this would mainly be to attend meetings when the feasibility and development strategy was being undertaken. It was stated that when the feasibility and development strategy was complete that a further report would be made back to Cabinet. RESOLVED That Cabinet notes the contents of the report and support the appointment of Capital Project Consultancy Ltd to undertake the preparation of a Feasibility and Development Strategy of the Gurnos Town Centre. Councillor W R Smith returned to the meeting.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
The purpose of this Report is to advise Councillors on a recently approved Welsh Assembly Government Physical Regeneration Fund (PRF) application to support the preparation of a Feasibility and Development Strategy for the Gurnos Town Centre, and to inform Members on the appointment of a consultant to undertake the commission.
Background
1.1I reported to Cabinet on the 11th November 2005 on the submission of funding applications to the Welsh Assembly Government (WAG) in October 2005 under the Physical Regeneration Fund initiative. This included a development funding application for Gurnos Town Centre to support the appointment of a consultant to undertake a Feasibility and Development Strategy for the Town Centre.
1.2Approval of the development funding application was received from WAG in January 2006. This has enabled the appointment of a suitable consultant to be progressed, principally in order to meet WAG’s requirement for initial expenditure on the project to be incurred during the current financial year.
2.0GURNOS TOWN CENTRE - FEASIBILITY AND DEVELOPMENT STRATEGY
2.1The aim of the Commission is to assess the feasibility of undertaking a major scheme of physical redevelopment within Gurnos Town Centre and to prepare a development strategy for taking forward delivery of the project. This is focused around the inherent structural and layout problems of the shopping centre, based on the possible demolition of the vacant high rise flats above the shops. It is likely that the project will be underpinned by the proposals of the Local Health Board to establish a Primary Health Care facility for General Practices on the site, which will enable the Health Centre and retail requirements to be fully integrated as part of the future development of the Town Centre.
2.2The key outcome of the study will be the preparation of a clearly defined programme of development work that will resolve many of the outstanding issues and assess the options for development that could include redevelopment and or refurbishment of the Town Centre. This will be supported by the preparation of a detailed operating strategy and business plan to demonstrate the viability and sustainability of the preferred development option. In addition, conceptual designs and a cost plan will be prepared, along with a funding strategy and advice on future ownership arrangements.
3.0APPOINTMENT OF CONSULTANT
3.1A budget of £25,000 has been approved by WAG for this project and guidance on this was included in the tender brief. Although a formal tendering process was not necessary, formal tenders were invited from four consultants.
3.2Four submissions were returned for the above commission on Friday 24th February 2006 as follows:
1. Capita Symonds: £21,750.00 2. University of Glamorgan: £22,500.00 3. Groundwork Merthyr and RCT £24,220.00 4. Capital Project Consultancy Ltd £25,000.00
3.3A selection panel meeting was held on the 6th March 2006 involving representatives from the Council and the 3 G’s Development Trust. (The Local Health Board was invited but was unable to attend). An evaluation exercise, based on an agreed scoring matrix was undertaken and showed that the tender bid submitted by Capital Project Consultancy Ltd scored highest. In particular, the client team was impressed by the consultant’s clear understanding of the tender brief, it’s innovative approach to carrying out the project, along with the breadth of experience of personnel within the project team. It was therefore concluded that the commission should be awarded to Capital Project Consultancy Ltd in the sum of £25,000.
3.4All works required within the brief are to be completed by June 2006, though Members will be kept informed of progress on the Strategy in due course.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.