Internal Audit reports - Major Financial Systems

Noted Finance 1 paper

Governance and Audit Committee noted this item on Tuesday 2 May 2006. Below is the council's own wording, with the papers it was decided on.

Item743

Resolved

RESOLVED (a) That the contents of the report be noted (b) That the message be reinforced that concerted action is required to implement Internal Audit recommendations in order that the opinion on internal audit controls can improve to at least satisfactory during 2006/2007 (c) That the Head of Benefits be requested to prepare a report on progress in addressing issues concerning the Pericles System and that he be invited to attend the next Audit Committee Meeting to give a presentation on this report.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Governance and Audit Committee, 131 pages

MERTHYR TYDFIL COUNTY BOROUGH COUNCIL

DATE WRITTEN 13 April 2006 REPORT AUTHOR Mark Thomas HEAD OF SERVICE Mark Thomas COMMITTEE Audit Committee COMMITTEE DATE 2 May 2006

TO: Chairman, Ladies and Gentlemen

Internal Audit Reports- Major Financial Systems

PURPOSE OF REPORT: To inform Councillors of the Internal Audit opinions on the internal controls operating in relation to the twelve major financial systems of the Council.

1.0INTRODUCTION AND BACKGROUND

1.1Councillors will recall that the Head of Internal Audit identified in his Annual Report to the Audit Committee in September 2006 that a number of unsatisfactory opinions were given on the internal controls operating in relation to the twelve major financial systems of the Council during the financial year 2004/05.

1.2It was clearly recognised that this was not a satisfactory position and a number of recommendations had been made in order to ensure improvements could be effected.

1.3Councillors requested that they be updated on progress in making improvements to internal controls in relation to the major financial systems. This report aims to do this by summarising the work of Internal Audit in auditing those systems during 2005/06 and giving an updated opinion on each system and the number of recommendations implemented at the time the audit work was carried out.

2.0FINDINGS

2.1Annex A attached is a summary of the opinions for each of the 12 major systems for 2005/06 along with opinions given for 2004/05. It can be seen that, overall, there has been an improvement in the opinions given which is summarised in table 1 below. Two systems were assessed as having good internal controls, three as being satisfactory but disappointingly 7 assessed as unsatisfactory. Whilst there has been an overall improvement it can be seen that there are still more systems assessed as being unsatisfactory than there are satisfactory or better. Table 1: Comparison of Internal Audit Opinions Given on the Major Financial Systems

Opinion 2003/04 2004/05 2005/06 A Very Good B Good 2 17% C Satisfactory 7 58% 5 42% 3 25% D Unsatisfactory 5 42% 6 50% 7 58% E Poor 1 8% Total 12 100% 12 100% 12 100%

2.2A number of issues however need to be highlighted as the opinion given does not give the full picture in terms of improvements made by services and does indicate some of the difficulties faced.

2.3In relation to the major systems managed by the Finance Audit & Risk Management Department, 2 systems have improved to a B opinion, 3 have remained satisfactory whilst 1 has deteriorated to a D opinion.

2.4The Accountancy Service should be commended for improving the internal controls in relation to the Bank Reconciliation & Short Term Loans & Investments Systems so that they achieved a B opinion.

2.5The Audit conducted in relation to the Creditor Payment System, which gave an assessment of D, was more in depth this time than ever before and identified a number of common issues affecting all Directorates to a greater or lesser degree and identified 29 recommendations which need to be implemented. Fourteen of these recommendations applied to the Central Payments function of the Authority but the remaining recommendations applied to a number of other service areas across the Council. More detail can be found in the summary report attached as Annex B.

2.6In terms of the percentage of recommendations not implemented this has ranged from high level of 80% to low level of 20%. Various staffing issues in the Accountancy Division has hampered progress in implementing a number of the recommendations. This is referred to in the summary reports attached as Annex B.

2.7As far as the major systems managed by the Customer Community Services Department is concerned all the systems were assessed as unsatisfactory which is disappointing. However this is an improvement from the previous year when the Housing Benefit and Council Tax Benefit system was assessed as poor.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit reports: Major Financial SystemsReport 131 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. Internal Audit reports - Major Financial SystemsThis decision
  2. Internal Audit Charter 2025/26Approved
  3. Annual Internal Audit Strategy & Plan 2025/26Approved
  4. Annual Internal Audit Report 2024/25Noted
  5. Internal Audit - Progress against the PlanNoted
  6. Internal Audit RecommendationsNoted

More from Merthyr Tydfil Governance and Audit Committee

All decisions
MeetingDecisionOutcome
28 Sep 2026 Peer Panel Performance Assessment - Response and Action PlanResolved that the report and draft action plan be noted and recommended to Council for approval. Noted Open
28 Sep 2026 Terms of ReferenceResolved that the Governance and Audit Committee be approved and reviewed annually. Approved Open
28 Sep 2026 Governance and Audit Committee Annual Report 2025/26Resolved that the Annual Report be noted, amended as appropriate in relation to the attendance record, and recommende... Noted Open
22 Jun 2026 Appointment of Chair and Vice ChairResolved; That Martin Veale continue as Chair and Colin Prosser continue as Vice-Chair of the Governance and Audit Co... Decided Open
1 Sep 2025 Time of Future MeetingsIt was agreed that future meetings would be moved to 5pm and if there was an issue with officer availability for any ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies