Merthyr Tydfil County Borough Council
Cabinet, Wednesday 14 June 2006 at 2.30pm

River Taff Corridor Enhancement: Strategy and Implementation Plan

Approved Executive 1 paper

Cabinet approved this item on Wednesday 14 June 2006. Below is the council's own wording, with the papers it was decided on.

Item56

Resolved

RESOLVED That following the presentation of the draft report by Austin Smith Lord Consultants, the River Taff Corridor Enhancement Strategy and Implementation Plan be approved by Cabinet, subject to comments received by Cabinet. That the implementation of the proposed phase 1 scheme be progressed in accordance with the priority projects outlined above subject to comments received by Cabinet.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 3 pages

Purpose of report

To inform and update Members on the draft final report for the River Taff Corridor Strategy and Implementation Plan and to seek approval for a recommended first stage implementation programme.

INTRODUCTION AND BACKGROUND

A report was received by Cabinet on the 25th January 2006, which approved the appointment of Austin Smith Lord Consultants to undertake a strategy and implementation plan for the enhancement of the River Taff corridor to the west of the town centre. The consultants were appointed to look at improvements to the river corridor environment adjacent to the Town Centre, through the development of public art, railings, lighting, furniture, enhancement of the physical appearance of the bridges and improved access to the river corridor.

RIVER TAFF CORRIDOR ENHANCEMENT

Austin Smith Lord consultants have presented the draft final report proposals to today’s Cabinet which provides an opportunity for Members comments to be incorporated into the preparation of the final Strategy. The Strategy has identified a range of projects that can be implemented in a phased approach when appropriate budgets become available. A phase 1 scheme has been designed in accordance with the strategy objectives. The first phase of works will indicate the changing importance of the river through exemplar projects setting the standard for the type and quality of work required throughout the whole of the river corridor.

The three priority exemplar projects are:

• Penry Street Bridge Improvements: to incorporate new railings, lighting, re- placement of stone copings and new paving. • Jackson’s Bridge Walkway Improvements (Taff Trail): to include resurfacing and widening of existing footpath, tree planting, new street furniture and railings.

• A4102 to Green Bridge Improvements: to provide an improved pedestrian route into the town centre for WAG employees by regrading and surfacing an existing desire line along with improved lighting, tree planting and boundary treatments.

Funding approval is currently being considered from the Welsh Assembly Government (Department of Enterprise, Innovation and Networks) to support this initial phase of implementation works this financial year. Part implementation of the strategy is also being considered through the Heads of the Valleys Programme as reported to Cabinet on 7th June and a detailed report on these proposals will be presented in due course. Proposals will be subject to further consultation, including where necessary in respect of Highway & Planning Consents and approval from the Environment Agency.

Financial implications

There are no financial implications to the Authority, as funding is being sought through the Welsh Assembly Government. However, officer time will be required in managing and assisting the consultants/contractors and providing baseline data and information in support of this work.

Recommendations

It is recommended that following presentation of the draft report by Austin Smith Lord Consultants, the River Taff Corridor Enhancement Strategy & Implementation Plan be approved by Cabinet, subject to comments received by Cabinet.

It is recommended that the implementation of the proposed phase 1 scheme be progressed in accordance with the priority projects outlined above subject to comments received by Cabinet.

JILL SHUKER DIRECTOR OF CORPORATE CENTRE

INTERNAL REPORT CONSULTATION:

The following officers have been consulted in respect of the proposals and recommendations set out in this report.

Chief Executive Deputy Chief Director of Director of Director of Chief Officer, Executive / Customer Integrated Integrated Adult Finance, Audit Director of Community Children’s Services and Risk Customer Services Services Management Corporate Services BACKGROUND PAPERS:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
River Taff Corridor Enhancement: Strategy and Implementation PlanReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. River Taff Corridor Enhancement: Strategy and Implementation PlanThis decision
  2. River Taff Central Link and Penderyn Square ContractDecided
  3. Town Centre Regeneration Programme: The naming of key elements of the River Taff Central LinkApproved
  4. Penderyn Square and River Taff Central Link Regeneration Projects - Proposed Permanent Traffic Regulation OrdersDecided
  5. Town Centre Regeneration Programme: Project Management Services for the River Taff Central Link and Penderyn Square SchemesApproved
  6. River Taff Central Link and Penderyn Square - Appointment of Contractor AmendmentApproved

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies