Culvert Maintenance

Decided Executive 1 paper

Cabinet decided this item on Wednesday 4 October 2006. Below is the council's own wording, with the papers it was decided on.

Item346

Resolved

RESOLVED - That works be undertaken to repair/replace the culverts and drainage provision set out as soon as practicable. - That funding in the estimated sum of £39,000 be directed from the car parking surplus and used as follows: Bryntaf Project £10,000 Oakland Street Project £ 9,000 Tai Mawr Lane Project £20,000 - That funding from the Glamorgan Engineering Consultancy profit share be directed in the sum of £9,000 as a contribution to the Oakland Street project. - That authorisation be given to contact the previous tenderers for the Bryntaf and Oakland Street projects in order to establish their willingness to stand by the previous bids. - That a further report be brought forward if appropriate in the event that actual costs exceed those set out above. - That a further report be presented in due course setting out other possible uses for car parking surplus revenue and the GEC profit share distribution. - That as a prudent measure, work on Scheme (c) (at Tai Mawr Lane) be delayed until works at the other locations have reached substantial completion.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 4 pages

MERTHYR TYDFIL COUNTY BOROUGH COUNCIL

DATE WRITTEN 13th September 2006 REPORT AUTHOR E Foley HEAD OF SERVICE E Foley COMMITTEE DIVISION Portfolio COMMITTEE Cabinet COMMITTEE DATE 4th October 2006

TO: Chairman, Ladies and Gentlemen

CULVERT MAINTENANCE

PURPOSE OF REPORT: To inform Councillors of three locations at which flooding has caused concern or is adjudged a serious threat and to recommend remedial action.

1.0INTRODUCTION AND BACKGROUND

1.1Councillors will be aware of my report to Cabinet on September 6th regarding the serious threat posed by a partially collapsed culvert at Chapel Street, Troedyrhiw. My recommendation for urgent remedial action was accepted and work has already commenced at the time of writing (September 13th).

1.2At the meeting on September 6th concern was expressed by several Councillors about a number of other culverts or drainage features which have flooded previously or which pose a threat of flooding and for which no funding has been identified. I was subsequently asked to bring forward a report on these potential “projects”, indicating the scope and estimated cost of the works. These details are set out below.

(a) Culvert adjacent to No.64A, Bryntaf, Aberfan. This is a culvert for which the Council is responsible in its capacity as Highway Authority. The inlet is considered close to collapse and almost inaccessible for cleansing by machine. Prompt action by an adjacent landowner has already prevented flooding on several occasions.

If a blockage occurred, the surcharge would enter the former Glamorgan Canal at a location where previous blockages have flooded properties in Walters Terrace. The estimated cost of repair (confirmed by tender in 2005) is approximately £10,000. This would include repairs to the inlet and installation of new entry grids.

(b) Culvert adjacent to 25 Oakland Street, Bedlinog.

This highway culvert drains a large mountain catchment area and has been the source of several flooding incidents. Several properties in Oakland Street have been flooded in prolonged heavy rain and the highway itself is regularly flooded in less severe storms.

The estimated cost of repair (confirmed by tender in 2005) is approximately £18,000. This includes new entry/inlet arrangements and an upsizing of the pipework beneath the road.

(c) Tai Mawr Lane, Merthyr.

The lane serves as an access for some 15 properties and offers an alternative access to Gellideg Estate. There is a natural dip or low spot in the lane which has flooded for many years during periods of heavy rain. In the past the problem has been alleviated by the creation of soakaways on the adjacent land but these have become blocked over time. The ability to disperse runoff has been further reduced due to the deposition of soil on adjacent land during the widening of Swansea Road during the mid 1990’s. The loss of capacity taken in conjunction with heavier rainfall patterns continues to cause flooding in only moderate rainfall and on several occasions this has resulted in closure of the road on safety grounds.

The flooding causes inconvenience to local residents (one of whom is disabled and relies upon a wheelchair) albeit access is still possible via Gellideg Estate. The regular flooding is also now causing the breakdown of the road fabric itself, creating large potholes in the process.

The estimated cost of constructing a new (deep) drain to conduct water away from the low spot is approximately £20,000.

2.0CONCLUSION

2.1There are powerful factors supporting the execution of remedial measures at the locations set out above as soon as practicable, as the Council is exposed to significant risk.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Culvert MaintenanceReport 4 pages DownloadRead as text

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies