Resolved
RESOLVED To defer the Local Development Plan pending a decision from the Welsh Assembly Government in regard to Merthyr Village following which a Special Council would be called to determine this application.
Planning, Regulatory and Licensing deferred this item on Tuesday 9 January 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED To defer the Local Development Plan pending a decision from the Welsh Assembly Government in regard to Merthyr Village following which a Special Council would be called to determine this application.
MERTHYR TYDFIL COUNTY BOROUGH COUNCIL
DATE WRITTEN 30th November 2006 REPORT AUTHOR C Edwards HEAD OF SERVICE N Davies COMMITTEE Special Planning & Regulatory COMMITTEE DATE 9th January 2007
TO: Chairman, Ladies and Gentlemen
MERTHYR TYDFIL LOCAL DEVELOPMENT PLAN 2006-2021 PREFERRED STRATEGY
PURPOSE OF REPORT: To seek Council’s approval of the Local Development Plan Preferred Strategy and all supporting documentation prior to them being published and made available for a statutory 6-week period of public consultation.
1.0INTRODUCTION
1.1Councillors will be aware of the statutory duty this Authority has under the Planning and Compulsory Purchase Act 2004 to prepare a Local Development Plan. The LDP is one of the Council’s most important strategic documents and sets out priorities for the development and use of land in the County Borough over the next 15 years and includes policies to assist in implementing them.
2.0INVOLVEMENT OF STAKEHOLDER GROUPS
2.1Preparation of the LDP has proceeded in accord with the provisions of the LDP Delivery Agreement which was approved by the Planning and Regulatory Committee on 21st December 2005 and by Full Council on 11th January 2006. The document was subsequently agreed with the Welsh Assembly Government on 14th February 2006.
2.2A significant part of the Delivery Agreement is given over to the Community Involvement Scheme, which outlines the processes and mechanisms to be used by the Authority in preparing its Plan.
2.3Part of those processes and mechanisms involved the setting up of: • 3 topic-specific Stakeholder Working Groups comprising key stakeholders and community representatives in Merthyr Tydfil, and • an LDP Steering Group comprising the Leader of the Council, two key Portfolio Councillors and relevant Chief Officers of the Authority. 2.4 The purpose of the Working Groups was to reach a consensus of opinion on priority issues pertinent to the Plan. The purpose of the Steering Group was to agree a final strategy for the LDP after due regard to the opinion of the Working Groups.
3.0PRIMARY CONSIDERATIONS FOR THE GROUPS
3.1Each of the groups met on three separate occasions between March and September 2006 and considered the following issues:-
• the overall context provided by national and regional guidance (e.g. the Wales Spatial Plan, Planning Policy Wales);
• the contents of the existing adopted Structure Plan and existing adopted Local Plan together with the unpublished UDP strategy;
• the contents of the local Community Strategy;
• current environmental, economic and social trends (the baseline situation);
• views of the local community, specific and general consultation bodies which were invited as part of early consultation on the LDP process.
4.0THE 3 POTENTIAL STRATEGY OPTIONS
4.1In the light of the above, the groups were then required to consider 3 potential strategy options.
4.2Each of the options related to the declining population levels in the County Borough and suggested different approaches to tackling this decline. The facts and figures that underpin each of the approaches are included in the LDP Background Paper on Population, Dwelling and Employment Land Forecasts, which is also being offered for Councillor’s consideration and approval.
4.3Each of the options was also subjected to independent Sustainability Appraisal by our appointed consultants to ensure that the strategy put forward is the most economically, socially and environmentally sustainable. The results of Sustainability Appraisal are included in the Initial Sustainability Appraisal Report and associated Non-Technical Summary which are two further documents being offered for consideration and approval.
i) Non-intervention Strategy This strategy option accepts that the County Borough will continue to experience a declining population throughout the plan period 2006-2021 and will seek to manage this as effectively as possible.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Merthyr Tydfil Local Development Plan 2006: 2021 Preferred StrategyReport | 6 pages | DownloadRead as text |
Follow Planning, Regulatory and Licensing at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Minutes of meeting Friday, 1 May 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. | Approved | Open |
| 2 Sep 2026 | Minutes of meeting Wednesday, 17 June 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. | Approved | Open |
| 2 Sep 2026 | Minutes of meeting Tuesday, 30 June 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. | Approved | Open |
| 2 Sep 2026 | Minutes of meeting Wednesday, 8 July 2026 of Licensing CommitteeResolved that: The minutes be approved as an accurate record. | Approved | Open |
| 2 Sep 2026 | Minutes of meeting Wednesday, 8 July 2026 of Planning, Regulatory and LicensingResolved that: The minutes be approved as an accurate record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.