Resolved
RESOLVED That based on the proposed programmes that £927,961 is allocated to Merthyr Vale Renewal Area with £822,039 allocated to Dowlais Renewal Area
Cabinet decided this item on Wednesday 7 February 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That based on the proposed programmes that £927,961 is allocated to Merthyr Vale Renewal Area with £822,039 allocated to Dowlais Renewal Area
To seek Cabinet’s approval for the allocation of housing resources for 2007/2008.
1.0INTRODUCTION
1.1The proposed arrangements for the distribution of Housing Capital Resources were contained in a letter received from the Welsh Assembly Government on 18th July 2006. This invited Local Authorities to submit specific bids for declared Renewal Areas by 5th September 2006.
1.2All other private sector housing costs, including Strategic Housing Schemes, should be funded through the General Capital Fund (GCF), including support for our Housing Renewal Policy that has been published under the terms of the Regulatory Reform (Housing Assistance) (England and Wales) Order 2003.
2.0FUNDING
2.1In common with previous years when allocating the amount of funding, WAG take into consideration the amount of resources that we plan to commit to support our published Housing Renewal Policy.
2.2Capital Grant will not be available unless we demonstrate that sufficient resources, including GCF is made available to deliver our published Housing Renewal Policy which must show a clear commitment to private sector housing renewal.
2.3When evaluating our bid for further funding the Assembly Government has assessed whether our objectives are realistic, achievable, involve other partnerships and take account of our past performance. 2.4 It is also expected that the Specific Capital Grant which has been allocated, should be supplemented by other Council resources that have been included in our General Capital Funding.
2.5The declared Renewal Areas at Merthyr Vale and Dowlais have been allocated a combined Specific Capital Grant of £1.75 million for 2007/2008, once again one of the highest allocations in Wales.
2.6This brings the aggregate total of successful funding applications that have been approved for the Renewal Areas over the last six years to an aggregate total of £10.85 million.
3.1This expenditure is covered by Specific Capital Grant from the Assembly, as referred to above.
4.1That based on the proposed programmes that £927,961 is allocated to Merthyr Vale Renewal Area with £822,039 allocated to Dowlais Renewal Area.
GARY THOMAS DIRECTOR OF CUSTOMER COMMUNITY SERVICES
INTERNAL REPORT CONSULTATION:
The following officers have been consulted in respect of the proposals and recommendations set out in this report.
Chief Executive Deputy Chief Director of Director of Director of Chief Officer, Executive / Integrated Integrated Corporate Finance, Audit Director of Children’s Adults’ Services Centre and Risk Customer Services Management Corporate Services
Title of Document(s) Document(s) Date Document Location
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Allocation of Specific Capital Grant 2007/2008Report | 2 pages | DownloadRead as text |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.