Resolved
RESOLVED That based on the conclusions drawn and the detail contained in the Appendix, the allocation of funds for 2007/08 is approved, combining to a total of approximately £843,600.
Cabinet approved this item on Wednesday 21 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That based on the conclusions drawn and the detail contained in the Appendix, the allocation of funds for 2007/08 is approved, combining to a total of approximately £843,600.
To seek approval for the proposed allocation of funds from monies available in 2006/07 and anticipated funds for 2007/08, and to provide an update on the Invest to Improve Fund.
1.0Introduction and Background
1.1Since 2001/02, Merthyr Tydfil County Borough Council has entered into a Policy Agreement with the Welsh Assembly Government. As part of the Agreement, payments under the heading of Performance Incentive Grant (PIG) have been made in order to help the process of meeting agreed targets, under defined headings.
In the last Agreement these have been:
• Helping More People into Jobs; • Improving Health; • Developing Strong and Safe Communities; and • Creating Better Jobs and Skills.
1.2As part of this process, by the start of the 2006/07 financial year, a ‘surplus’ of £285,000 had accrued. The latest figure projected to the end of this year is approximately £300,000.
1.3A further amount of approximately £600,000 for the year 2007/08 is available but clearly dependent on achieving the performance standards detailed in the Policy Agreement. Indeed, failure to meet all of the criteria will jeopardise this final payment. 1.4. Directors and Managers are fully aware of this strict requirement and are continuing to afford the Performance Indicators contained in the Agreement their fullest attention.
2.0Performance Indicator coverage
2.1The broad areas covered are:
• Regeneration • Secondary School Attendance • Community Safety • Looked After Children • Sustainable Development • Equalities • Procurement and Efficiencies • Energy Conservation • Substance Misuse • Homelessness • Social Care
3.0Allocation of Funds
3.1All Directorates were given the opportunity to make their proposals for the allocation of the Performance Incentive Grant monies which, when submitted, are to a total of £900,000 (which includes a contingency amount of approximately £56,000).
3.2In the first instance as a prime requirement, to meet performance standards, the Appendix details in “green” those areas agreed by Executive Board which would secure the final payment. As Councillors can see they reflect the areas detailed above.
3.3The “red” areas are those put to Cabinet as not to be approved.
3.4Additionally, monies had been allotted to support further areas of development to provide income into, and not merely expenditure out of, the Invest to Improve Fund. This was the essential principle of the Invest To Improve Fund, presented to Cabinet in a Report in June 2006.
4.0Invest to Improve Update
4.1The original Cabinet Report referred to approved expenditure in the following areas: with a number of appointments made on two year fixed term contracts, that of:
- £100,048 allocated for the employment of an Efficiency Manager;
- £87,684 allocated for the employment of two Sundry Debtor Officers; - £69,397 allocated for the employment of one temporary Legal Assistant;
- £43,842 allocated for the employment of an Assistant Procurement Officer;.
- £69,397 allocated for the employment of one External Funding Officer. .
At that time a commitment would also be met of:
- £20,000 for Town centre marketing and promotional activities; - £30,000 for management development.
4.2The progress on the appointment of the above posts is as follows:
- The employment of an Efficiency Manager did not take place despite placing and receiving six applications for the post. None of the potential candidates met the calibre required to fulfil such a position;
- Two Sundry Debtor Officers were appointed in October 2006;
- The monies allocated for the employment of one temporary Legal Assistant has been retained but at a lesser amount;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Allocation of Policy Agreement: Performance Incentive Grant 2007 and update on the Invest to Improve FundReport | 4 pages | DownloadRead as text |
PDF |
Appendix 1Appendix 1 | 4 pages | Download |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.