RESOLVED To support in principle the appointment of Allen Construction Consultancy to provide the necessary Project Management, Quantity Surveyors, Architectural, Structural Engineering and Building Services Engineer in the sum of £107,250.00 to support the implementation of the Gurnos Town Centre Regeneration Project subject to further discussions with the Head of Estates taking place before award.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
The purpose of this Report is to update Members on progress in respect of the Gurnos Town Centre Regeneration Project and to seek Members’ approval on the appointment of consultancy support in the implementation of the Project.
1.0INTRODUCTION AND BACKGROUND
1.1Following the approval of funding through the Welsh Assembly Government sponsored “Physical Regeneration Fund” in January 2000 work has progressed in taking forward the Gurnos Town Centre project for implementation. The approved funding of £1.5m is to be spread over the 3 financial years of the programme, with £500,000 to be expended in each year commencing in the current financial year.
1.2The scheme proposes the refurbishment of the currently vacant block of flats for office and community related uses. It is also proposed to extend the existing shop units to provide new shop fronts and a new pitched roof. Proposals also include new car parking provision to the front of the shops, along with hard and soft landscaping and new secure storage compounds to the rear.
1.3In order to support the Council in implementing the project proposals, a range of consultancy support services is required. This includes Project Management, Quantity Surveying, Architectural, Structural Engineering and Building Services Engineer. 2.0 Consultancy Appointment
2.1Through the original tendering process, Capital Project Consultancy was commissioned by the Council in March 2006 to undertake an initial feasibility study and subsequent development work which enabled a PRF application to be submitted to WAG for funding approval. In order to meet the Council’s own procurement regulations, it has been necessary to go out to tender for the additional consultancy work required. Based on an estimate of likely costs, expressions of interest have been sought, in the first instance, through the publication of an OJEU Notice.
2.2A Notice inviting expressions of interest was published in the European Journal on the 18th June 2007, with a deadline for return of bids by 12 Noon on the 19th July 2007. A total of 13 submissions were received. These were assessed against the criteria set-out in the Notice. A scoring matrix was used as the basis for this evaluation and as a result, 3 submissions scored sufficiently highly to be taken forward to the next tender stage. (The OJEU Notice had indicated that a shortlist of between 2 and 4 consultants would be invited to tender).
2.3Subsequently, as part of the formal tender process, a tender brief was issued to the 3 short-listed consultants on the 24th July 2007 with a deadline for the return of tenders of 12 Noon on the 9th August 2007. Tenders were received from the 3 consultants by the prescribed date, in the following amounts:
1. £107,250.00 2. £181,000.00 3. £215,950.00
2.4In view of the range of bids received, further clarification was sought from the 2 lowest tenderers on the split of costs between each of the services to be provided, to ensure that all areas were covered and to assess more closely the relative costs assigned to each service. (This information had been included within the tender bid of the highest tenderer).
2.5Based on this further assessment and on the criteria set-out in the tender brief, namely, the consultants ability to meet the requirements of the brief, cost competitiveness and the approach to carrying out the project, it is considered that the lowest tender, submitted by the Allen Construction Consultancy in the sum of £107,250.00 be accepted in providing the necessary consultancy service support for the Council in the implementation of the Gurnos Town Centre Regeneration Project.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.