RESOLVED That Councillors note (again) the petition submitted in May and the subject of the report on June 27 th That the contract continues as soon as practicable (dependent upon Network Rail formal consent). That the complainant residents be informed of their right to seek compensation for loss of amenity.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
DATE WRITTEN 3rd October 2007 REPORT AUTHOR Mark Robinson/E Foley HEAD OF SERVICE E Foley COMMITTEE DIVISION Portfolio COMMITTEE Cabinet COMMITTEE DATE 17th October 2007
TO: Chairman, Ladies and Gentlemen
TREVITHICK TRAIL, MERTHYR TYDFIL AND FOOTBRIDGE AT DARREN LAS
PURPOSE OF REPORT: To remind Cabinet of receipt of a petition opposing the construction of a new bridge over the Merthyr Tydfil – Cardiff railway line at Darren Las (Mount Pleasant) and to advise Cabinet of the consultation process carried out.
1.0INTRODUCTION AND BACKGROUND
1.1In March 2002 the Engineering Department of the Council was requested to examine the feasibility of constructing a walking and cycling trail along the line of the former Penydarren Tramroad.
1.2Initial estimates were prepared for grant application and accepted; the Engineering Department then proceeded to submit a planning application for the whole length of the trail (i.e. from Trevithick’s Tunnel near Brodawel to Pontygwaith near Edwardsville).
1.3The planning application was submitted on 11th October 2002 and included two new bridges as part of the scheme; one over the A4060(T) at Pentrebach and one over the Merthyr Tydfil – Cardiff railway line at Black Lion Level Crossing, Darren Las.
1.4As part of the usual planning process, notices were placed by the Planning Department along the length of the proposed trail in October 2002 and a public notice was also placed in the Merthyr Express dated 25th October 2002. Further notices were placed along the relevant length of the proposed trail in November 2002 and the consultation period extended to afford the opportunity for objections to be submitted. 1.5 The application was considered by the Planning and Licensing Committee on 22nd January 2003 and a permission was issued, dated 27th January 2003. No objections to the scheme proposals were received.
1.6Funding for the scheme was obtained from the Welsh European Funding Office and was granted in stages according to the individual Wards through which the trail passes.
1.7Funding for the first Plymouth Ward portion of the Trail was granted on 3rd June 2004 as part of larger grant allocations for the “Trevithick 2004” celebrations. A contract was prepared in August 2004 for this section of the Trail with work on site commencing in November 2004 and completion in September 2005.
1.8A second tranch of funding for the works required in Merthyr Vale Ward was sought in July 2005 and a letter of confirmation of this funding was received in March 2006. Detailed design work for this section then commenced undertaken by the Engineering Department of Merthyr Tydfil CBC. Part of the design work entailed ensuring that the bridge over the railway fully complied with Network Rail and Disability Discrimination Act requirements; conflict with existing statutory undertaker’s apparatus also had to be resolved.
1.9A contract for the works was prepared in July 2006 and tenders invited from six potential bidders.
1.10Cabinet approval for the chosen contractor was given on 20th September 2006, in the sum of £413,800.43.
1.11Work commenced on site in October 2006 and a letter dated 3rd October 2006, explaining the nature of the works was delivered to some 50 properties in Darren Las and Mount View which were closest in proximity to the works. No response was received from any of the properties.
1.12Work continued until early January 2007 at which time weather conditions deteriorated and were such that the works were temporarily suspended. The steelwork fabrication for the structure over the railway line continued at the fabricator’s works in Newport.
1.13In the course of the next few months a number of visits to local residents properties took place as a result of telephone calls about material being tipped in readiness for the earthwork embankment leading up to the new bridge. The calls expressed concern at the appearance of the interim embankment and fears of future loss of amenity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.