Full Council, Wednesday 17 October 2007 at 5.30pm

Highway Maintenance

Approved Committee 2 papers

Full Council approved this item on Wednesday 17 October 2007. Below is the council's own wording, with the papers it was decided on.

Item345

Resolved

RESOLVED That Council approve the proposed financing of the Highways Repair Programme as identified within the report.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Full Council, 4 pages

Purpose of report

To update Cabinet on the present position in respect of Highways Maintenance requirements and to seek a resolution on additional financial investment for a programme of targeted repairs.

1.0INTRODUCTION

1.1There are presently 1,216 works orders outstanding requiring repair to the highway infrastructure. These works include potholes, damaged kerbs, drainage gulleys etc.

1.2New defects arise on average at a rate of 7 per day which effectively maintains the backlog.

1.3The estimated cost of carrying out works to address this defect backlog amounts to £291,457 for structural defects and £60,000 to address the more urgent drainage works totalling £351,457.

1.4The estimated cost of carrying out major highway resurfacing programmes including carriageways, footpaths and extensive kerb renewals, assessed by Highways Officers is £3,118,465. The annual Local Authority Road Maintenance Survey identifies through mechanical means an average of £4.7 million per Authority as the funding shortfall in Wales.

Financial implications

2.1Council has recently approved funding to the amount of £350,000 through Biffa funds to contribute towards the identified defects and resurfacing requirements. 2.2 A comprehensive list of prioritised works has been identified with costings from the structural repair register and these are attached as Table 1 (Value £200,114) and Table 2 (Value £252,568).

3.00INITIAL WAG ROAD REPAIR GRANT LIST 07/08 (CARRIAGE RESURFACING)

Route Location Estimate B4255 Oakland Street, Bedlinog £25,000 B4254 Gelligaer Road, Trelewis £20,000 B4254 Shingrig Junction, Trelewis £36,000 B4285 Bells Hill, Merthyr Vale £40,000 B4285 Bridge Street/Aberfan Road, Aberfan £27,000 B4285 Carlton Terrace, Bronheulog, Troedyrhiw £30,000 B4254 Cardiff Road, Treharris £22,000 TOTAL £200,000

3.1A WAG grant of £182,000 has been received as part of their response to assist in the crisis facing the failing highway condition in Wales. This funding is ring fenced and can only be used on roads which have been analysed by the scanner system of road condition assessment. The scanner system involves highlighting failed road structures and through a priority system, an action list is submitted to WAG to comply with the conditions of grant release. The grant is limited in value and therefore we have to carefully manage the spend. WAG approved the programme of works above which is now nearing completion.

Recommendations

4.1That Cabinet considers further investment into Highways Maintenance based on the prioritised listings enclosed.

GARY THOMAS DIRECTOR OF CUSTOMER COMMUNITY SERVICES

INTERNAL REPORT CONSULTATION:

The following officers have been consulted in respect of the proposals and recommendations set out in this report.

Chief Executive Deputy Chief Director of Director of Director of Director of Executive / Integrated Integrated Adult Corporate Finance Director of Children’s Services Centre Customer Services Corporate Services

Background papers

Title of Document(s) Document(s) Date Document Location EXTRACT FROM HIGHWAYS MAINTENANCE STRUCTURAL REPAIR REGISTER FOR SET VALUE ESTIMATES – REPORT TO COUNCIL 2007

Key for work proposal:-

CW = Carriageway Resurfacing FW = Footway Resurfacing FWP = Footway Paving K = New Kerbing.

TABLE 1 – PROPOSED SCHEMES TO A VALUE OF APPROXIMATELY £200K

Actual cost £200,114

Street Name Work Area Location Priority Location Cost £ North Sixth Avenue FW K Galon Uchaf 1 59,200 Gwaunfarren Road FW By Bishop Hedley School 2 23,800 NORTH TOTAL 83,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HIGHWAYSMAINTENANCEMTLJReport 4 pages DownloadRead as text
PDF
Highway MaintenanceReport 4 pages Download

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. Highway MaintenanceThis decision
  2. Highways, Winter Maintenance & Street Lighting – Performance UpdateNoted
  3. Welsh Purchasing Consortium Framework for the supply of Highway Maintenance and Traffic Management ProductsApproved
  4. Highways MaintenanceApproved
  5. Highways MaintenanceApproved
  6. Highways MaintenanceDecided

More from Merthyr Tydfil Full Council

All decisions
MeetingDecisionOutcome
22 Oct 2026 Allocations Policy for Community HousingResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 MTCBC Receiving and Awarding Grants PolicyResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved; That the recommendations as contained within the report be approved. Approved Open
22 Oct 2026 Youth Service Statutory 5-Year Strategic Plan 2027-32Resolved; That the recommendations as contained within the report be approved Approved Open
30 Sep 2026 Healthy Organisation Strategy: Workforce Strategy 2026-2029Resolved; That the recommendations as contained within the report be approved Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies