CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Merthyr Tydfil County Borough Council
Full Council, Wednesday 23 January 2008 at 5.30pm

Connecting SE Wales - Shared Services Project

Approved Committee 1 paper

Full Council approved this item on Wednesday 23 January 2008. Below is the council's own wording, with the papers it was decided on.

Item585

Resolved

RESOLVED That Council approves the recommendations of the Connecting South East Wales Partnership Board and agrees to: Move forward to the next stage and the completion of a Detailed Business Case. Use this stage to clearly identify best practice so that individual Authorities can simplify and standardise current processes to gain benefits regardless of whether they move forward into a shared services operation. Ensure the next stage provides a robust assessment so that Authorities can make an informed decision about whether to join a chared services operation.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Full Council, 7 pages

Purpose of report

To seek Council’s approval to the recommendation of the Connecting South-East Wales Partnership Board to move forward to the next stage and the completion of a detailed business case.

1.0INTRODUCTION AND BACKGROUND

1.1The report attached in full at Appendix 1, Connecting SE Wales – Shared Services Project, was presented to Cabinet this afternoon.

1.2Previous reports have been presented to Cabinet and Council regarding this project:

• A report was presented to Cabinet and subsequently to Council on 26th July 2006 approving the Council’s involvement in the feasibility study, which incorporated 3 phases – initial feasibility, business case and feasibility framework. • A further report was presented to Cabinet on 13th June 2007, to agree the recommendations from phase 1 and to proceed to the Outline Business Case (phases 2 & 3).

Financial implications

2.1A contribution of £25,000 is required from this Council towards the match funding provided by the Welsh Assembly Government. In light of the settlement for 2008/9 it is proposed that the contribution is found from the anticipated underspend in the current financial year (2007/8).

3.0MONITORING AND EVALUATION

3.1An update report will be brought to Council in 6 months time. 4.0 RECOMMENDATION(S)

4.1That subject to agreement by Cabinet this afternoon, Council approves the recommendations of the Connecting South East Wales Partnership Board and agrees to:

• Move forward to the next stage and the completion of a Detailed Business Case. • Use this stage to clearly identify best practice so that individual Authorities can simplify and standardise current processes to gain benefits regardless of whether they move forward into a shared services operation. • Ensure the next stage provides a robust assessment so that Authorities can make an informed decision about whether to join a shared services operation.

JILL SHUKER DIRECTOR OF CORPORATE CENTRE

INTERNAL REPORT CONSULTATION:

The following officers have been consulted in respect of the proposals and recommendations set out in this report.

Chief Executive Deputy Chief Director of Director of Director of Director of Executive / Customer Integrated Integrated Adult Finance, Audit Director of Community Children’s Services and Risk Customer Services Services Management Corporate Services

Background papers

Title of Document(s) Document(s) Date Document Location Shared Services Project File Various Room 425 Appendix 1

MERTHYR TYDFIL COUNTY BOROUGH COUNCIL

DATE WRITTEN 13th December 2007 REPORT AUTHOR Jill Shuker HEAD OF SERVICE Jill Shuker COMMITTEE DIVISION Strategic COMMITTEE Cabinet COMMITTEE DATE 23rd January 2008

TO: Chairman, Ladies and Gentlemen

Connecting SE Wales – Shared Services Project

To seek Cabinet’s agreement to the recommendation of the Connecting South-East Wales Partnership Board to move forward to the next stage and the completion of a detailed business case.

1.0INTRODUCTION AND BACKGROUND

1.1Cabinet will be aware of the background to this report through previous reports and policy documents describing the context, namely:

• ‘Making The Connections’ (November 2004) • Beyond Boundaries/Citizen-Centred Local Services for Wales (Beecham, June 2006) • Shared Service Feasibility Study, report to Cabinet (July 2006) • ‘Making the Connections – Delivering Beyond Boundaries’ (November 2006). • CSEW Shared Services Strategic Outline Case (March 2007) • Connecting South East Wales: Shared Services Project, report to Cabinet (June 2007)

1.2The policy documents from WAG and the Merthyr Tydfil Cabinet reports include the strong promotion of collaboration in terms of services in order to achieve continuous service improvement and the on going efficiencies that will be required over the medium to long term. 2.0 ISSUES AND FINDINGS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Connecting SE Wales: Shared Services ProjectReport 7 pages DownloadRead as text

At this meeting

Whole meeting
585Connecting SE Wales - Shared Services ProjectThis decision
586Concert at Cyfarthfa CastlePrivate

On this subject at Merthyr Tydfil

Search all
  1. Connecting SE Wales - Shared Services ProjectThis decision
  2. South East Wales Improvement Collaborative(SEWIC) - Making the Connections: Connecting Social ServicesDecided
  3. South East Wales Improvement Collaboration (SEWIC) - 'Making the Connections: Connecting Social Services' - Programme Briefing PaperDecided
  4. Connecting South East Wales Shared ServicesAgreed
  5. Connecting S E Wales - Shared Services ProjectApproved
  6. Connecting South East Wales - Shared ServicesApproved

More from Merthyr Tydfil Full Council

All decisions
MeetingDecisionOutcome
22 Oct 2026 Allocations Policy for Community HousingResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 MTCBC Receiving and Awarding Grants PolicyResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved; That the recommendations as contained within the report be approved. Approved Open
22 Oct 2026 Youth Service Statutory 5-Year Strategic Plan 2027-32Resolved; That the recommendations as contained within the report be approved Approved Open
30 Sep 2026 Healthy Organisation Strategy: Workforce Strategy 2026-2029Resolved; That the recommendations as contained within the report be approved Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies