Merthyr Tydfil County Borough Council
Full Council, Wednesday 15 October 2008 at 5.30pm

Project Management Costs to Develop the Lifelong Learning Project Strategic Outline Case

Agreed Committee 1 paper

Full Council agreed this item on Wednesday 15 October 2008. Below is the council's own wording, with the papers it was decided on.

Item315

Resolved

RESOLVED that Council agrees to the project management support role costs of no more than £7,000.00 as outlined within the report. Council accepts the grant of £25,000 from DCELLS in support of the preparations of the Strategic Outline Case.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Full Council, 5 pages

Financial implications

2.1In relation to the project management support role costs of £7,000 are required and funding for this has been identified from within the corporate authority budget.

2.2The grant funding from DCELLLS of up to £25,000 will have no Financial Implications for this Council. 3.0 RECOMMENDATIONS

2.1That Council agrees to the project management costs outlined in this report.

2.2Council accepts the grant of £25,000 from DCELLS in support of the preparation of the Strategic Outline Case.

ALISTAIR NEILL CHIEF EXECUTIVE

INTERNAL REPORT CONSULTATION:

The following officers have been consulted in respect of the proposals and recommendations set out in this report.

Deputy Chief Director of Director of Director of Director of Director of Executive & Integrated Integrated Adult Customer Corporate Finance, Audit Director of Children’s Services Community Centre and Risk Customer Services Services Management Corporate Services

Background papers

Title of Document(s) Document(s) Date Document Location No Background papers used APPENDIX 1

MERTHYR TYDFIL COUNTY BOROUGH COUNCIL

DATE WRITTEN 1st October 2008 REPORT AUTHOR Alistair Neill HEAD OF SERVICE Alistair Neill COMMITTEE DIVISION Strategic COMMITTEE Cabinet COMMITTEE DATE 1st October 2008

TO: Chairman, Ladies and Gentlemen

PROJECT MANAGEMENT COSTS TO DEVELOP THE LIFELONG LEARNING

PROJECT STRATEGIC OUTLINE CASE

Purpose of report

To seek Cabinet approval for the shared project management costs between 4th October and 31st December 2008 supporting development of the Lifelong Learning Project Strategic Outline Case, to be met from under-spend in Corporate Authority budgets, and to advise Cabinet of additional project support being externally funded by DCELLS.

1.0INTRODUCTION

1.1The Lifelong Learning Project, with its focus on a Merthyr Learning Quarter, is being progressed to meet Council objectives and to deliver against the changing sets of requirements laid out by DCells. DCells has clarified in July 2008 that the required process needs to follow the ‘Treasury Green Book’ 5-stage model. The next stage of this is the Strategic Outline Case, known as the SOC. This stage will precede development of a business case.

1.2The recommended time-frame for development of the Strategic Outline Case is in the period ending 15th January 2009.

1.3The subsequent stage, up to 31st March 2009, will focus on the development of the Outline Business Case (known as the OBC), leading towards the Final Business Case preceding any formal approach for funding. 1.4 Separately, the Council will receive a future report, as per the June 2008 Council resolutions, providing the opportunity to consider the detailed business case prior to any formal approach for funding.

Background

2.1The Project Manager reports to the Project Board. His contract ends on 3rd Oct 2008. Beyond that date, funding will need to be found by the key partners, Merthyr Tydfil County Borough Council and the University of Glamorgan, in order to retain the Project Manager in his current temporary role.

2.2The current time-frame is critical to the project, hence the importance of retaining the Project Manager in this role.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project Management Costs to Develop the Lifelong Learning Project Strategic Outline CaseReport 5 pages DownloadRead as text

At this meeting

Whole meeting
312aMinutes of meeting Friday, 12th September, 2008 of Licensing CommitteeOn the agenda 312bMinutes of meeting Wednesday, 17th September, 2008 of CabinetOn the agenda 312cMinutes of meeting Wednesday, 17th September, 2008 of Full CouncilOn the agenda 312dMinutes of meeting Wednesday, 24th September, 2008 of Planning and Regulatory CommitteeOn the agenda 312eMinutes of meeting Wednesday, 1st October, 2008 of CabinetOn the agenda 312fMinutes of meeting Thursday, 2nd October, 2008 of Licensing CommitteeOn the agenda 314Notice of MotionDecided
315Project Management Costs to Develop the Lifelong Learning Project Strategic Outline CaseThis decision
316Merthyr Tydfil County Borough Council compliance to Fire Safety Order 2005Approved 317New byelaws for Acupuncture, Tattooing, Semi Permanent Skin Colouring, Cosmetic Piercing and ElectrolysisApproved 318Creation of Policy and introduction of Associated Fees for undertaking the Statutory Street Naming and Numbering FunctionApproved 319Natural Environmental and Rural Communities (NERC) Act 2006Approved 320Merthyr Tydfil Local Development Plan 2006 - 2021 Deposit PlanApproved 321Financial Support - Gorwelion Management CommitteeNoted 322Support for Campaign for Ghurkha RightsDecided 323Draft Corporate Plan 2008-2011Approved 324Improvement Report 2008Decided 325Customer Focus Action PlanApproved 326Trecatti Landfill site Profit ShareApproved 327Approval of Draft Single Children and Young People's Plan 2008-11Approved 328Edwardsville Pool - TreharrisAgreed 329Housing Stock TransferNoted 330To deal with any other urgent business or correspondenceApproved

On this subject at Merthyr Tydfil

Search all
  1. Project Management Costs to Develop the Lifelong Learning Project Strategic Outline CaseThis decision
  2. Formal Approval Of A New Welsh Government Sustainable Management Scheme (Sms) Project Entitled Taf Bargoed Catchment RestorationApproved
  3. Town Centre Regeneration Programme: Project Management Services for the River Taff Central Link and Penderyn Square SchemesApproved
  4. Corporate Risk No. 13 - Project Management 2011/12Decided
  5. Project Management Costs to develop the Lifelong Learning Project Strategic Outline CaseAgreed

More from Merthyr Tydfil Full Council

All decisions
MeetingDecisionOutcome
22 Oct 2026 Allocations Policy for Community HousingResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 MTCBC Receiving and Awarding Grants PolicyResolved; That the recommendations as contained within the report be approved Approved Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved; That the recommendations as contained within the report be approved. Approved Open
22 Oct 2026 Youth Service Statutory 5-Year Strategic Plan 2027-32Resolved; That the recommendations as contained within the report be approved Approved Open
30 Sep 2026 Healthy Organisation Strategy: Workforce Strategy 2026-2029Resolved; That the recommendations as contained within the report be approved Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies